File #: 14-2025    Version: 1 Name: KSE - Change Order #2 - Mt Prospect Ave & Broadway Construction Management
Type: Resolution Status: Filed
File created: 11/24/2014 In control: Engineering
On agenda: 1/7/2015 Final action: 1/21/2015
Title: Dept/ Agency: Engineering Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Professional Services Contract Purpose: Construction Management and Inspection Services Entity Name: KS Engineers, P.C. Entity Address: 494 Broad Street, 4th Floor, Newark, New Jersey 07102 Contract Amount: $78,355.20 Funding Source: UEZ Contract Period: Extending contract period until April 30, 2015 Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Addition Information: Change Order No. 2; Original contract amount $199,717.78 Deferred 7R4-a 010715
Sponsors: Council of the Whole
``Title
Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Professional Services Contract
Purpose: Construction Management and Inspection Services
Entity Name: KS Engineers, P.C.
Entity Address: 494 Broad Street, 4th Floor, Newark, New Jersey 07102
Contract Amount: $78,355.20
Funding Source: UEZ
Contract Period: Extending contract period until April 30, 2015
Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Addition Information:
Change Order No. 2; Original contract amount $199,717.78
Deferred 7R4-a 010715

body

WHEREAS, Resolution 7R4-B, adopted October 5, 2011, authorized the Director of the Department of Engineering to accept the bid proposal and execute Contract No. 15-2011PS, City-wide Streetscape - Phase I, Construction Management and Inspection Services, Mt. Prospect Avenue and Lower Broadway Projects, with KS Engineers, P.C., for the amount of $199,717.78; and

WHEREAS, a Notice to Proceed was issued on September 11, 2012, which date constituted the commencement of the contract term, which was 365 days hence; and

WHEREAS, Change Order #1/Amendment #1, Resolution 7R4-A, adopted April 2, 2014, authorized the Director of the Department of Engineering to extend the contract period through December 31, 2014; and

WHEREAS, work started in October of 2012, at which time English Paving was the contractor for performing the construction work for the Project, but the contract between English Paving and the City was terminated. However, KS Engineers, P.C. had already provided work on this project in the amount of $17,186.40. This equaled 186 hours of work; and

WHEREAS, due to additional work required for the construction of the repair of vaults on Lowe...