Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Change Order/Amend Resolution 7R12-c adopted on July 10, 2019
Purpose: Valve Inspection, Testing, and Condition Assessment Report, for the City of Newark Distribution and Transmission System
Entity Name: Pure Technologies US, Inc., d/b/a Wachs Water Services
Entity Address: 8920 State Route 108, Suite D, Columbia, Maryland 21045
Contract Amount: Not to exceed $1,352,106.00
Funding Source: 2019 Budget/Department of Water and Sewer Utilities/NW037-750-07502-71280-B2019
Contract Period: One (1) year from the date of issuance of a Notice to Proceed, extended by an additional 365 calendar days
Contract Basis: (X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Original Resolution 7R12-c adopted on July 10, 2019, awarded a contract in an amount not to exceed $1,352,106.00, for the period of one (1) year from the date of the issuance of the Notice to Proceed.
Change Order #1 will extend the completion time by 365 calendar days.
body
WHEREAS, Resolution 7R12-c adopted on July 10, 2019, authorized the award of Contract 08-WS2018, to Pure Technologies US, Inc., 8920 State Route 108, Suite D, Columbia, Maryland 21045, in the amount of $1,352,106.00 in accordance with the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq.; and
WHEREAS, during the course of the Project, the contractor had a delayed start and encountered unforeseen conditions as a result of the COVID-19 global pandemic and Public Health Emergency, which caused additional delays, such that 365 calendar days is required to complete the Project; and
WHEREAS, Contract 08-WS2018 is to be amended with no change in contract amount, and 365 calendar days to be added to the contract...