Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Final Quantities Change Order #2/Amend Resolution 7R12-a(S) adopted on March 10, 2020, and 7R12-d(AS) adopted on December 29, 2020
Purpose: To execute a Contract Close Out Change Order #2 for Phase-7(A) Lead Service Line Replacement Contract 29-WS2023.
Entity Name: Roman E&G Corporation
Entity Address: 14 Ogden Street, Newark, New Jersey 07104
Contract Amount: Not to exceed $7,511,669.21
Funding Source: Capital Budget/Department of Water and Sewer Utilities
Contract Period: 550 calendar days from the date of the issuance of a written Notice to Proceed to final completion
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-a(S) adopted on March 10, 2020 awarded a contract in an amount not to exceed $6,261,670.00 for a period of 280 calendar days to final completion from the date of the issuance of a written Notice to Proceed.
Resolution 7R12-d(AS) adopted on December 29, 2020 authorized Change Order #1, which increase the original contract by $1,250,000.00 for a new total contract amount not to exceed $7,511,670.00, with no change to the contract completion period.
Contract Close out Change Order #2 will reduce the contract amount by $0.79 for a new total contract amount not to exceed $7,511,669.21 and increase the contract period by 270 calendar days for a new completion period of 550 calendar days from the date of the issuance of a written Notice to Proceed to final completion.
body
WHEREAS, 7R12-a(s) adopted on March 10, 2020, authorized the award of Contract 29-WS2023, Phase-7(A) Lead Service Line Replacement, to Roman E&G Corporation, 14 Ogden Street, Newark, New Jersey 07104, in the amount of $6,261,670.00 for a pe...