7R12-b  
					
					Action: (X) Ratifying (X) Authorizing (X) Amending  
					Type of Service: Contract 10-WS2020, Process and Operational  
					Upgrades at the Pequannock Water Treatment Plant: Closeout Change  
					Order #3  
					Purpose: To execute Close-out Change Order #3 Process and  
					Operational Upgrades at the Pequannock Water Treatment Plant -  
					Contract 10-WS2020.  
					Entity Name: Spectraserv, Inc.  
					Entity Address: 75 Jacobus Avenue, Kearny, New Jersey 07032  
					Contract Amount: Not to exceed $20,543,284.08  
					Funding Source: 2021Capital Budget/Department of Water and Sewer  
					Utilities Utilities/NW041-21W-21W00-94710-B2021  
					Contract Period: 928 calendar days to final completion from the date  
					of the issuance of a written Notice to Proceed  
					Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS  
					(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ  
					( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a  
					Additional Information:  
					Original Resolution 7R12-a(S) adopted on July 20, 2021, awarded a  
					contract in an amount not to exceed $19,789,000.00, for a period of 560  
					calendar days from the date of the issuance of a written Notice to  
					Proceed.  
					Resolution 7R12-a(S) adopted on December 13, 2022, authorized  
					Change Order #1, which increased the contract amount by $357,075.07  
					for a total contract amount not to exceed $20,146,075.07 and increased  
					the contract period by 130 calendar days for new completion contract  
					period of 690 calendar days from the date of the issuance of a written  
					Notice to Proceed.  
					Resolution 7R12-a adopted on September 7, 2023, authorized Change  
					Order #2, which increased increase the contract amount by $397,209.01  
					for a new total contract amount not to exceed $20,543,284.08, and  
					increased the contract period by 137 calendar days for a new contract  
					period of 827 calendar days from the date of the issuance of a written  
					Notice to Proceed.  
					Contract Close-out Change Order #3 will close the Project with no  
					change in the contract amount of $20,543,284.08, but will increase the  
					contract period by 101 calendar days for a new contract period of 928  
					calendar days from the date of the issuance of a written Notice to  