Action: ( X ) Ratifying (X) Authorizing ( X ) Amending
Type of Service: Change Order/Amend Resolution #1
Purpose: To provide an amendment to Resolution 7R3-e 09/05/2024 and
to Contract #2023-10, Newark Ironbound Roundabout Safety
Improvements Federal Project.
Entity Name: Berto Construction, Inc.
Entity Address: 625 Leesville Avenue, Rahway, New Jersey, 07065
Contract Amount: Not to exceed $1,343,772.65
Funding Source: 2025 Budget/Department of
Engineering/NW011-110-1107-A-71930 - B2025 (which is a new funding
source) and NW051-G24-E24H0-A-71930-B2024. The original funding
source NW011-110-1107-A-71930-B2024 was cancelled.
Contract Period: Original contract period June 16, 2025 to October 05,
2025 extended 117 consecutive calendar days to January 31, 2026
Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Original Resolution 7R3-e adopted on September 5, 2024.
The Grant Award was $1,456,374.50.
The initial contract amount was $1,298,268.17. The amended contract
amount is $1,343,772.65 ($1,246,120.97 for construction covered by
grant) and $97,651.68 (2025 Budget/Department of Engineering, Division
of Traffic and Signals NW011-110-1107-A-71930 - B2025, a new funding
source for “Traffic Director, Police”, non- participating item).
The $210,253.53 is being reserved for Change Orders
This Change Order #1/Amendment will extend the contract period date for
final completion of the contract for construction, increase the not-to-exceed
contract amount, make full payment to Berto Construction Inc., and
close-out with NJDOT/FHWA a new final completion date January 31,
2026