File #: 17-1434    Version: 1 Name: Stone, Crushed
Type: Resolution Status: Adopted
File created: 7/25/2017 In control: Administration
On agenda: 12/20/2017 Final action: 12/20/2017
Title: Dept/ Agency: Administration/Division of Central Purchasing Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Bid Contract(s) Purpose: To provide crushed stone to the City Description: Stone, Crushed Entity Name(s)/Address(s): 1. Stavola Construction Materials, Inc., 175 Drift Road, Tinton Falls, New Jersey 07724 2. Stone Industries, Inc., 400 Central Avenue, Haledon, New Jersey 07538 3. Tilcon New York, Inc., 9 Entin Road, Parsippany, New Jersey 07054 Contract Amount: $390,000.00 Funding Source: 2017 Budget/Departments of Public Works and Water and Sewer Utilities Account Code Line: NW011-060-0605-83720-B2017-Public Works/Sanitation and Demolition NW011-060-0603-83720-B2017-Public Works/Parks and Grounds NW037-750-7502-83720-B2017-Water and Sewer Utilities Contract Period: To be established for a period not to exceed two years Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable C...
Sponsors: Council of the Whole

Title

Dept/ Agency:  Administration/Division of Central Purchasing

Action:  (   ) Ratifying     (X) Authorizing     (   ) Amending

Type of Service:  Bid Contract(s)

Purpose:  To provide crushed stone to the City

Description: Stone, Crushed

Entity Name(s)/Address(s):

1. Stavola Construction Materials, Inc., 175 Drift Road, Tinton Falls, New Jersey 07724

2. Stone Industries, Inc., 400 Central Avenue, Haledon, New Jersey 07538

3. Tilcon New York, Inc., 9 Entin Road, Parsippany, New Jersey 07054

Contract Amount: $390,000.00

Funding Source:  2017 Budget/Departments of Public Works and Water and Sewer Utilities

Account Code Line:

NW011-060-0605-83720-B2017-Public Works/Sanitation and Demolition

NW011-060-0603-83720-B2017-Public Works/Parks and Grounds

NW037-750-7502-83720-B2017-Water and Sewer Utilities

Contract Period:  To be established for a period not to exceed two years

Contract Basis: (X) Bid   (   ) State Vendor   (   ) Prof.  Ser.   (   ) EUS  

(   ) Fair & Open   (   ) No Reportable Contributions   (   ) RFP   (   ) RFQ

(   ) Private Sale   (   ) Grant   (   ) Sub-recipient   (   ) N/A   

Additional Information: 

Advertisement Date April 11, 2017

Bids Solicited: Five (5)

Bids Received: Three (3)

body

 

WHEREAS, on April 11, 2017, the City of Newark through its Supervising Procurement Specialist, QPA, advertised to solicit bids for contractor(s) to provide Stone, Crushed, to the Departments of Public Works and Water and Sewer Utilities, as per the bid proposal attached hereto; and

 

WHEREAS,                      the Division of Central Purchasing also distributed five (5) bid proposal packages to the prospective vendors following the date of advertisement; and

 

WHEREAS, on April 27, 2017, three (3) bids were received in response to this advertisement; and

 

WHEREAS, the Director of Public Works and the Assistant Director of the Department of Water and Sewer Utilities recommends that a multiple award be made to Stavola Construction Materials, Inc. , Stone Industries, Inc., and Tilcon New York, Inc., the responsive and responsible bidders; and

 

WHEREAS, the Supervising Procurement Specialist, QPA, concurs with the recommendations from the Director of Public Works and the Assistant Director of the Department of Water and Sewer Utilities, that a multiple award be made to Stavola Construction Materials, Inc., Stone Industries, Inc., and Tilcon New York, Inc., the responsive, responsible bidders, and

 

 WHEREAS, pursuant to N.J.S.A. 40A;11-24, the bidders consented to holding prices bid for consideration, until such time as an award is made, as the law permits; and

 

WHEREAS, pursuant to N.J.S.A.19:44A-20.5 et seq., solicitations through public bidding in accordance with N.J.S.A.40A:11-1, et seq., meets the requirements of the fair and open process.

 

NOW, THEREFORE BE IT RESOLVED, BY THE MUNICIPAL COUNCIL OF THE CITY OF NEWARK, NEW JERSEY, THAT:

 

1.     The Mayor and/or his designee, the Supervising Procurement Specialist, are hereby authorized to enter into a contract with Stavola Construction Materials, Inc., 175 Drift Road, Tinton Falls, New Jersey 07724, to receive line items #1, 2 and 8 (various sizes & types) for year one and year two, 2.) Stone Industries, Inc., 400 Central Avenue, Haledon, New Jersey 07538, to receive line items # 3, 5, 6, 7 and 8 (various sizes & types) for year one and year two and 3.) Tilcon New York, Inc., 9 Entin Road, Parsippany, New Jersey 07054, to receive line items #4, and 8 (various sizes & types) for year one and year two, to provide Stone, Crushed to the City, whose bids were received on the advertised due date and determined to be the responsive, responsible bidders, in accordance with the bid specifications. The term of the contract will be established for a period not to exceed a two (2) year term, pursuant to N.J.S.A.40A:11-15, at a cost not to exceed $390,000.00 for three (3) vendors.

 

2.                     There shall be no amendment or change of this contract without the approval of the Municipal Council by resolution.

 

3.                     There shall be no advance payment on this contract in accordance with N.J.S.A. 40A:5-16.  Funds for 2017 and subsequent years are contingent upon appropriations; pursuant to N.J.A.C. 5:30-5.5(d).

 

 4.                     This is an open-ended contract to be used as needed during the term of contract.  Thus, for any and all expenditures against this contract, a certification of the availability of sufficient funds, as required by N.J.A.C. 5:30-5.5(b)(2), shall be executed before a contractual liability is incurred each time an order is placed, for account code lines covering the amount of the order:

NW011-060-0605-83720-B2017- Public Works/Sanitation and Demolition

NW011-060-0603-83720-B2017- Public Works/Parks and Grounds

NW037-750-7502-83720-B2017 - Water and Sewer Utilities

This contract shall not exceed $390,000.00 for a period to be established not to exceed two (2) years for three vendors.                                           

 

5.                     A duly executed copy of the contract shall be forthwith filed in the Office of the City Clerk by the Purchasing Director.

 

6.                     If required by State Law, the City Clerk shall provide the appropriate notice of the award of this contract, to the State Comptroller no later than 20 business days following such award, in accordance with N.J.S.A. 52:15C-10 and the Notice of the Office of the State Comptroller dated May 7, 2008.

 

 

STATEMENT

 

This contract is awarded to Stavola Construction Materials, Inc., Stone Industries, Inc., and Tilcon New York, Inc., to provide Stone, Crushed to the City of Newark, at a cost not to exceed $390,000.00 for a period to be established not to exceed two (2) years, for three (3) vendors.