File #: 13-1802    Version: 1 Name: Change Order #1: Spiniello Companies - Brick Sewer Rehabilitation Program Phase VI (G) (Contract #07R-WS2009)
Type: Resolution Status: Adopted
File created: 9/18/2013 In control: Water Sewer Utility
On agenda: 8/6/2014 Final action: 9/17/2014
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing (X ) Amending Type of Service: Change Order/Amend Resolution 7R12-b July 7, 2011 Purpose: To execute Contract Close-Out and Final Quantities under Change Order #1 Entity Name: Spiniello Companies Entity Address: 354 Eisenhower Parkway, Livingston, New Jersey 07039 Contract Amount: Original Contract Amount of $4,245,230.00, to be reduced by $382,327.82 for a Final Contract Amount of $3,862,902.18 Funding Source: City of Newark/Water and Sewer Utilities Budget/Low-interest Loan from New Jersey Department of Environmental Protection (NJDEP) and New Jersey Environmental Infrastructure Trust (NJEIT) Contract Period: One Hundred and Eighty (180) calendar days extended by Fourteen (14) calendar days Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ...
Sponsors: Council of the Whole
Title
Dept/ Agency: Water and Sewer Utilities
Action:  (   ) Ratifying     (X) Authorizing     (X ) Amending
Type of Service:  Change Order/Amend Resolution 7R12-b July 7, 2011  
Purpose: To execute Contract Close-Out and Final Quantities under Change Order #1
Entity Name:  Spiniello Companies
Entity Address:  354 Eisenhower Parkway, Livingston, New Jersey 07039
Contract Amount:  Original Contract Amount of $4,245,230.00, to be reduced by $382,327.82 for a Final Contract Amount of $3,862,902.18
Funding Source:  City of Newark/Water and Sewer Utilities Budget/Low-interest Loan from New Jersey Department of Environmental Protection (NJDEP) and New Jersey Environmental Infrastructure Trust (NJEIT)     
Contract Period:  One Hundred and Eighty (180) calendar days extended by Fourteen (14) calendar days
Contract Basis: ( X  ) Bid   (   ) State Vendor   (   ) Prof.  Ser.   (   ) EUS   
(   ) Fair & Open   (   ) No Reportable Contributions   (   ) RFP   (   ) RFQ
(   ) Private Sale   (   ) Grant   (   ) Sub-recipient   (   ) n/a
Additional Information:
Funded by the New Jersey Environmental Infrastructure Financing Program FFY2010/SFY2011                
Final Quantities Change Order #1 and Contract Close-Out reducing the total contract amount by $382,327.82 and extending the contract period by fourteen (14) days  
 
body
 
      WHEREAS, Resolution 7R12-b adopted on July 7, 2011 by the Municipal Council authorized the award of Contract 07R-WS2009 (Rebid) Brick Sewer Rehabilitation Program Phase VI (G) Sewer Rehabilitation with Spiniello Companies, of 354 Eisenhower Parkway, Livingston, New Jersey 07039, in the amount of $4,245,230.00, in accordance with Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and
 
WHEREAS, Contract 07R-WS2009 (Rebid) was completed and is to be closed out with a total of $379,827.82 to be reduced for unused quantities, and a credit of $2,500.00, with a net amount of $382,327.82 to be reduced from the total contract amount with extending the contract period by fourteen (14) calendar days; and
 
WHEREAS,      the Department of Water and Sewer Utilities wishes to execute a Final Quantities Change Order #1 to Contract 07R-WS2009 (Rebid) Brick Sewer Rehabilitation Program Phase VI (G) Sewer Rehabilitation, with Spiniello Companies, of 354 Eisenhower Parkway, Livingston, New Jersey 07039, reducing the contract by $382,327.82, bringing the total contract amount to $3,862,902.18, and extending the contract completion time by fourteen (14) calendar days.
 
NOW, THEREFORE, BE IT RESOLVED BY THE MUNICIPAL COUNCIL OF THE CITY OF NEWARK, NEW JERSEY, THAT:
 
1.         The Municipal Council hereby authorizes the Mayor and/or his designee, the Acting Director of the Department of Water and Sewer Utilities, to execute a Final Quantities Change Order #1 to Contract 07R-WS2009 (Rebid) Brick Sewer Rehabilitation Program Phase VI (G) Sewer Rehabilitation with Spiniello Companies, of 354 Eisenhower Parkway, Livingston, New Jersey 07039, reducing the contract by $382,327.82, bringing the total contract amount to $3,862,902.18, and extending the contract completion time by fourteen (14) calendar days.
 
2.         No additional funds are required for the Final Quantities Change Order #1 since this is a reduction change order.
 
3.      A fully executed copy of the Final Quantities Change Order #1 shall be filed in the Office of the City Clerk by the Acting Director of the Department of Water and Sewer Utilities.
 
4.      A fully executed copy of the Final Quantities Change Order #1 shall be filed with the New Jersey Department of Environmental Protection (NJDEP) by the Acting Director of the Department of Water and Sewer Utilities.
 
5.      If required by State Law, the City Clerk shall provide the appropriate notice of the award of this contract to the State Comptroller no later than twenty (20) days following such award, in accordance with N.J.S.A. 52:15C-10 and the Notice of the Office of the State Comptroller dated May 7, 2008.
 
 
STATEMENT
 
This resolution hereby amends and authorizes the Mayor and/or his designee, the Acting Director of the Department of Water and Sewer Utilities, to enter into and execute a Final Quantities Change Order #1 to Contract 07R-WS2009 (Rebid) Brick Sewer Rehabilitation Program Phase VI (G) Sewer Rehabilitation, with Spiniello Companies, of 354 Eisenhower Parkway, Livingston, New Jersey 07039, reducing the contract by $382,327.82, bringing the total contract amount to $3,862,902.18, and extending the contract completion time by fourteen (14) calendar days.