Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X ) Amending
Type of Service: Change Order/Amend Resolution # 7R12-b Adopted April 15, 2026
Purpose: To execute Contract Change Order #3 for the Rehabilitation of the Pequannock Aqueducts - Contract #14-WS2023
Entity Name: Hutton Construction, LLC
Entity Address: 41 Village Park Road, Cedar Grove, New Jersey 07009
Contract Amount: Increase of $857,191.99 for total contract amount not to exceed $15,733,229.21
Funding Source: 2023 Budget/Department of Water and Sewer Utilities/Business Unit: NW041, Dept. 23W, Div/Proj 23W00, Account #94710, Budget Ref. B2023
Contract Period: 1,102 calendar days from the date of the written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A
Additional Information:
Resolution 7R12-a(as) adopted on June 5, 2024 awarded a contract in an amount not to exceed $13,119,347.00 for a period of 640 calendar days from the date of the written Notice to Proceed to final completion.
Change Order #1 Resolution 7R12-a adopted on July 2, 2025 increased the contract amount by $1,093,931.41 for a new total contract amount not to exceed of $14,213,278.41, and will increase the contract period by 482 calendar days for a new completion period of 1,102 calendar days from the date of Notice to Proceed to final completion.
Change Order #2 Resolution 7R12-b adopted on April 15, 2026 increased the contract amount by $662,758.81 for a new total contract amount not to exceed $14,876,037.22 for a period of 1,102 calendar days from the date of Notice to Proceed to final completion.
Change Order #3 will increase the contract amount by $857,191.99 for a new total contract amount not to exceed $15,733,229.21 for a period of 1,102 calendar days from the date of Notice to Proceed to final completion.
body
WHEREAS, 7R12-a(as) adopted on June 5, 2024, authorized the Director of the Department of Water and Sewer Utilities to execute Contract 14-WS2023, Rehabilitation of Pequannock Aqueducts, with Hutton Construction, LLC (“Hutton”), 41 Village Road, Cedar Grove, New Jersey 07009, in the amount of $13,119,347.00 for a period of 620 calendar days from the date of the written Notice to Proceed, in accordance with the Local Public Contracts Law, N.J.S.A. 4A:11-1 et seq: and
WHEREAS, 7R12-a adopted on July 2, 2025, authorized the Director of the Department of Water and Sewer Utilities to execute Change Order #1 to Contract 14-WS2023, Rehabilitation of Pequannock Aqueducts, with Hutton and increased the contract amount by $1,093,931.41 for a new total contract amount not to exceed $14,213,278.41, and increased the contract period by 782 calendar days for a new completion period of 1,102 calendar days from the date of the written Notice to Proceed to final completion; and
WHEREAS, 7R12-b adopted on April 15, 2026 authorized the Director of the Department of Water and Sewer Utilities to execute Change Order #2 to Contract 14-WS2023, Rehabilitation of Pequannock Aqueducts, with Hutton and increased the contract amount by $662,758.81 for a new total contract amount not to exceed $14,876,037.22 for a period of 1,102 calendar days from the date of Notice to Proceed to final completion; and
WHEREAS, Change Order #3 is the result of differing site conditions which were discovered at multiple project locations, as well as additional scope improvements for the improvement of future maintenance and operations, installation of new air release valves among other unforeseen changes commencing on or around May 1, 2026, as detailed in the attached Engineer’s Letter and Contract Modification Proposal and Acceptance form; and
WHEREAS, pursuant to N.J.A.C. 5:30-11 et eq. Contract No. 14-WS2023 is to be amended to include an increase in the contract amount by Eight Hundred Fifty-Seven Thousand, One Hundred Ninety-One Dollars and Ninety-Nine Cents ($857,191.99) for a new contract amount of Fifteen Million, Seven Hundred Thirty-Three Thousand, Two Hundred Twenty-Nine Dollars and Twenty-One Cents ($15,733,229.21) and no extension on final completion of 1,102 calendar days from the date of the written Notice to Proceed and;
WHEREAS, the Department of Water and Sewer Utilities wishes to enter into and execute a Contract Change Order #3 to Contract 14-WS2023, the Rehabilitation of the Pequannock Aqueducts with Hutton with an increase in the contract amount by Eight Hundred Fifty-Seven Thousand, One Hundred Ninety-One Dollars and Ninety-Nine Cents ($857,191.99) for a new contract amount of Fifteen Million, Seven Hundred Thirty-Three Thousand, Two Hundred Twenty-Nine Dollars and Twenty-One Cents ($15,733,229.21) and no extension on final completion of 1,102 calendar days from the date of the written Notice to Proceed.
NOW, THEREFORE, BE IR RESOLVED BY THE MUNICIPAL COUNCIL OF THE CITY OF NEWARK, NEW JERSY, THAT:
1. The Mayor of the City of Newark and/or his designee, the Director of the Department of Water and Sewer Utilities, are authorized to enter into and execute Contract Change Order #3 to Contract 14-WS2023, Rehabilitation of the Pequannock Aqueduct with Hutton Construction, LLC, 41 Village Park Road, Cedar Grove, New Jersey 07009 to increase the contract amount by Eight Hundred Fifty-Seven Thousand, One Hundred Ninety-One Dollars and Ninety-Nine Cents ($857,191.99) for a new contract amount of Fifteen Million, Seven Hundred Thirty-Three Thousand, Two Hundred Twenty-Nine Dollars and Twenty-One Cents ($15,733,229.21) and no extension on final completion of 1,102 calendar days from the date of the written Notice to Proceed.
2. Change Order # 3 is ratified from May 1, 2026, to the date of adoption of this authorizing resolution.
3. Attached hereto is a Certification of Funds from the Chief Financial Officer, which states that funds in the amount of Eight Hundred Fifty-Seven Thousand, One Hundred Ninety-One Dollars and Ninety-Nine Cents ($857,191.99), are available in the Water and Sewer Utilities Capital Budget under Business Unit NW041, Department ID 23W, Division/Project 23W00, Account #94710, Budget Ref. B2023 and which shall be filed along with the original Resolution in the Office of the City Clerk.
4. A fully executed copy of the Change Order #3 shall be filed in the Office of the City Clerk by the Director of the Department of Water and Sewer Utilities.
5. A fully executed copy of the Change Order #3 shall be filed with the New Jersey Department of Environmental Protection (NJDEP) by the Director of the Department of Water and Sewer Utilities.
6. If required by State Law, the City Clerk shall provide the appropriate notice of the award of this contract to the State Comptroller, no later than twenty (20) business days following such award, in accordance with N.J.S.A. 52:15C-10 and the Notice of the Office of the State Comptroller dated May 7, 2008.
STATEMENT
This Resolution ratifies, amends and authorizes the Mayor of the City of Newark and/or his designee, the Director of the Department of Water and Sewer Utilities, to enter into and execute Contract Change Order #3 to Contract 14-WS2023, Rehabilitation of the Pequannock Aqueducts with Hutton Construction, LLC, 41 Village Park Road, Cedar Grove, New Jersey 07009, increasing the contract amount by $857,191.99 for a total amount of $15,733,229.21, and no extension on final completion of 1,102 calendar days from the date of the written Notice to Proceed.