File #: 25-0221    Version: 1 Name: Resolution Change Order# 4 Contact 07-WS2016 Coppola Services Inc.
Type: Resolution Status: Adopted
File created: 2/10/2025 In control: Water Sewer Utility
On agenda: 2/19/2025 Final action: 2/19/2025
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying ( X ) Authorizing ( ) Amending Type of Service: Change Order/Amend Resolution # Resolution 7R12-a adopted on February 5, 2025 Purpose: Change Order #4 increasing contract amount and contract period for CSO Solids/Floatables Control Measures Netting Facilities at Peddie Ditch, Site 025 Contract #07-WS2016. Entity Name: Coppola Services, Inc. Entity Address: 28 Executive Parkway, Ringwood, New Jersey 07456 Contract Amount: Not to exceed $3,730,538.02 Funding Source: Capital Budget/Department of Water and Sewer Utilities/Business Unit: NW038, Dept. 800, Div./Proj. 8007, Account #71970, Budget Ref. B2025 Contract Period: 795 calendar days to final completion from the date of the issuance of a written Notice to Proceed Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( X ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant...

Title

Dept/ Agency:  Water and Sewer Utilities

Action:  (   ) Ratifying     ( X  ) Authorizing     (   ) Amending

Type of Service: Change Order/Amend Resolution # Resolution 7R12-a adopted on February 5, 2025

Purpose: Change Order #4 increasing contract amount and contract period for CSO Solids/Floatables Control Measures Netting Facilities at Peddie Ditch, Site 025 Contract #07-WS2016.

Entity Name:  Coppola Services, Inc.

Entity Address:  28 Executive Parkway, Ringwood, New Jersey 07456

Contract Amount:  Not to exceed $3,730,538.02

Funding Source:  Capital Budget/Department of Water and Sewer Utilities/Business Unit: NW038, Dept. 800, Div./Proj. 8007, Account #71970, Budget Ref. B2025

Contract Period:  795 calendar days to final completion from the date of the issuance of a written Notice to Proceed

Contract Basis: ( X  ) Bid   (   ) State Vendor   (  ) Prof.  Ser.   (   ) EUS  

( X  ) Fair & Open   (   ) No Reportable Contributions   (   ) RFP   (   ) RFQ

(   ) Private Sale   (   ) Grant   (   ) Sub-recipient   (   ) n/a

Additional Information:

Resolution 7R12-c (as) adopted on November 2, 2022, awarded a contract in an amount not to exceed $3,169,890.00, for a period of 180 calendar days from the date of the issuance of a written Notice to Proceed.

 

Resolution 7R12-a adopted on November 1, 2023, authorized Change Order #1, which increased the contract amount by $14,840.22 for a new total contract amount not to exceed $3,184,730.22, with no extension on final completion from the date of the issuance of the Notice to Proceed.

 

Resolution 7R12-a adopted on May 22, 2024, authorized Change Order #2, which increased the contract amount by $53,781.24 for a new total contract amount not to exceed $3,238,511.46, extended the contract period by 222 calendar days for a new completion Period of 402 Calendar days from the date of Notice to Proceed to final completion.

 

Resolution 7R12-a adopted on February 5, 2025 authorized Change Order # 3, which increased the contract amount by $121,352.42 for a new total contract amount not to exceed $3,359,863.88, extended the contract period by 337 calendar days for a new contract completion period of 739 calendar days from the date of Notice to Proceed to final completion.

 

Change Order #4 will increase the contract amount by $370,674.14 for a new total contract amount not to exceed $3,730,538.02, and increase the contract period by 56 calendar days for a new contract period of 795 calendar days to final completion from the date of the issuance of a written Notice to Proceed. 

body

 

WHEREAS, Resolution 7R12-c(as) adopted on November 2, 2022, authorized the Director of the Department of Water and Sewer Utilities to enter into Contract 07-WS2016, CSO Solids/Floatables Control Measures Netting Facilities at Peddie Ditch, Site 025  (“Contract 07-WS2016”) with Coppola Services, Inc., 28 Executive Parkway, Ringwood, New Jersey 07456, in the amount of $3,169,890.00 for a period of (180) calendar days to final completion from the date of the written Notice to Proceed; and

 

WHEREAS, Resolution 7R12-a adopted on November 1, 2023, authorized Change Order #1 to Contract 07-WS2016 with Coppola Services, Inc., for an increased amount of $14,840.22 for a new total contract amount not to exceed $3,184,730.22 and no extension on final completion from the date of the issuance of the Notice to Proceed; and

 

WHEREAS, Resolution 7R12-a adopted on May 22, 2024, authorized Change Order #2 to Contract 07-WS2016 with Coppola Services, Inc., for an increased amount of $53,781.24 for a new total contract amount not to exceed $3,238,511.46 with an additional 222 Calendar days for a new completion period of 402 calendar days to final completion from the date of the issuance of the Notice to Proceed; and

 

WHEREAS, Resolution 7R12-a adopted on February 5, 2025, authorized Change Order #3 to Contract 07-WS2016 with Coppola Services, Inc., for an increased amount of $121,352.42 for a new total contract amount not to exceed $3,359,863.88 with an additional 337 Calendar days for a new completion period of 739 calendar days to final completion from the date of the issuance of the Notice to Proceed; and

 

WHEREAS, as a result of improvements performed under the original scope of work a need has arisen to: [i] remove from the invert of Peddie Ditch within the contact limits, sediment, settled material that exceed the elevation of the newly poured concrete pile cap at the Peddie Ditch Netting Facility and is not native soil,  [ii] erosion control and stabilization material, if necessary, to support the ditch bank following the removal of sediment along its edge, and [iii] testing, stockpiling and removal of material confirmed to be eligible of disposal; and

 

WHEREAS, pursuant to NJAC 5:30-11 et seq. Contract 07-WS2016, is to be amended with an increase net amount of Three Hundred Seventy Thousand Six Hundred and Seventy-Four Dollars and Fourteen Cents ($370,674.14) to cover the required removal of Peddie Ditch Sediment and an additional (56) calendar days for a new contract period of 795 to final completion from the date of the issuance of a written Notice to Proceed; and

 

WHEREAS,                     the Department of Water and Sewer Utilities wishes to enter into and execute a Contract Change Order #4 to Contract 07-WS2016, with Coppola Services, Inc., with an increase in the contract amount by Three Hundred Seventy Thousand Six Hundred and Seventy-Four Dollars and Fourteen Cents ($370,674.14) for a new contract amount of Three Million Seven Hundred Thirty Thousand Five Hundred Thirty Eight Dollars and Two Cents  ($3,730,538.02) and an additional (56) additional calendar days for a new contract period of 795 calendar days to final completion from the date of the issuance of a written Notice to Proceed.

 

NOW, THEREFORE, BE IT RESOLVED BY THE MUNICIPAL COUNCIL OF THE CITY OF NEWARK, NEW JERSEY, THAT:

 

1.                     The Mayor of the City of Newark and/or his designee, the Director of the Department of Water and Sewer Utilities, is authorized to enter into and execute Contract Change Order #4 to Contract 07-WS2016, CSO Solids/Floatables Control Measures Netting Facilities at Peddie Ditch, Site 025, with Coppola Services, Inc., 28 Executive Parkway, Ringwood, New Jersey 07456, to: [i] remove from the invert of Peddie Ditch within the contact limits, sediment, settled material that exceed the elevation of the newly poured concrete pile cap at the Peddie Ditch Netting Facility and is not native soil,  [ii] erosion control and stabilization material, if necessary, to support the ditch bank following the removal of sediment along its edge; and [iii] testing, stockpiling and removal of material confirmed to be eligible of disposal, increasing the contract amount by Three Hundred Seventy Thousand Six Hundred and Seventy-Four Dollars and Fourteen Cents ($370,674.14) bringing the contract amount to Three Million Seven Hundred Thirty Thousand Five Hundred Thirty Eight Dollars and Two Cents  ($3,730,538.02) and extending the contract completion time by (56) calendar days to final completion from the date of the issuance of the Notice to Proceed for a new contract period of 795 Calendar days to final completion from the date of the issuance of the Notice to Proceed.

 

2.                           Attached hereto is a Certification of Funds from the Chief Financial Officer, which states that funds in the amount of Three Hundred Seventy Thousand Six Hundred and Seventy-Four Dollars and Fourteen Cents ($370,674.14) are available in the Water and Sewer Utilities Capital Budget under Business Unit NW038, Department ID 800, Division/Project 8007, Account # 71970, Budget Ref. B2025 and which shall be filed along with the original Resolution in the Office of the City Clerk.

 

3.                      A fully executed copy of the Change Order #4 shall be filed in the Office of the City Clerk by the Director of the Department of Water and Sewer Utilities.

 

4.                     A fully executed copy of the Change Order #4 shall be filed with the New Jersey Department of Environmental Protection (NJDEP) by the Director of the Department of Water and Sewer Utilities.

 

5.                     If required by State Law, the Acting City Clerk shall provide the appropriate notice of the award of this contract to the State Comptroller, no later than twenty (20) business days following such award, in accordance with N.J.S.A. 52:15C-10 and the Notice of the Office of the State Comptroller dated May 7, 2008.

 

STATEMENT

 

This Resolution authorizes the Mayor of the City of Newark and/or his designee, the Director of the Department of Water and Sewer Utilities, to enter into and execute Contract Change Order #4 to Contract 07-WS2016, CSO Solids/Floatables Control Measures Netting Facilities at Peddie Ditch, Site 025 with Coppola Services, Inc., , to: [i] remove from the invert of Peddie Ditch within the contact limits, sediment, settled material that exceed the elevation of the newly poured concrete pile cap at the Peddie Ditch Netting Facility and is not native soil,  [ii] erosion control and stabilization material, if necessary, to support the ditch bank following the removal of sediment along its edge; and [iii] testing, stockpiling and removal of material confirmed to be eligible of disposal, increasing the contract amount by $370,674.14 for a total contract amount of $3,730,538.02, with an additional (56)  calendar days for a new contract period of 795 Calendar days to final completion from the date of the issuance of the Notice to Proceed.