File #: 19-0708    Version: 1 Name: Phase-1B Sewer Cleaning and Rehabiilitation Contract 13-WS2017 - Montana Construction Corp.
Type: Resolution Status: Adopted
File created: 4/20/2019 In control: Water Sewer Utility
On agenda: 6/11/2019 Final action: 6/11/2019
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Bid Contract Purpose: Phase-1(B) Sewer Cleaning and Rehabilitation - Contract 13-WS2017 Entity Name: Montana Construction Corp., Inc. Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644 Total Contract Amount: $6,743,122.00 Funding Source: 2011 Budget/Department of Water and Sewer Utilities/044-11G-11SAO-94710 B2011 Contract Period: 320 days from a written Notice to Proceed Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A Additional Information: Bids Distributed: Ten (10) Bids Received: Two (2)
Sponsors: Council of the Whole
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Bid Contract
Purpose: Phase-1(B) Sewer Cleaning and Rehabilitation - Contract 13-WS2017
Entity Name: Montana Construction Corp., Inc.
Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644
Total Contract Amount: $6,743,122.00
Funding Source: 2011 Budget/Department of Water and Sewer Utilities/044-11G-11SAO-94710 B2011
Contract Period: 320 days from a written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A
Additional Information:
Bids Distributed: Ten (10)
Bids Received: Two (2)
body

WHEREAS, the City of Newark advertised Contract 13-WS2017 Phase-1(B) Sewer Cleaning and Rehabilitation located at various locations in the City of Newark, on December 17, 2018; and

WHEREAS, the Department of Water and Sewer Utilities ("Department") distributed ten (10) bid packages to prospective vendors following the date of bid advertisement; and

WHEREAS, on January 17, 2019, the Department received two (2) bids for said project in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, Montana Construction Corp., Inc., 80 Contant Avenue, Lodi, New Jersey 07644 submitted the lowest responsive and responsible bid, according to the specifications and in the total amount of $6,694,622.00 for the base bid, and in the total amount of $48,500.00 for the supplemental bid, with a combined base bid and supplemental bid total amount of $6,743,122.00; and

WHEREAS, the City of Newark wishes to accept the lowest responsible bid submitted by Montana Construction Corp., Inc. on January 17, 2019, and execute Contract 13-WS2017 Phase-1(B) Sewer Cleaning and Rehabilitation, with Montana Construction Corp., Inc., 80 Contant Avenue, Lodi, New Jersey 07644, for the combined base bid and supplemental bid total amount not to exceed $6,743,122; and

WHEREAS, the Municipal Council adopted the Contractor Pay-to-Play Reform Ordinance, R.O. 2:4-22C, which forbids the award of a contract of a Business Entity, as defined therein, which has made or solicited political contributions to Newark Municipal Candidates, office holders having ultimate responsibility for the award of a contract; candidate committees of the aforementioned candidates, and political or political party committees of the City of Newark or County of Essex; and continuing political committees or political action committees regularly engaged in the support of the City of Newark Municipal or County of Essex elections; and certain other political party or candidate committees, in excess of certain thresholds; and
WHEREAS, this contract is for an amount over $17,500.00 and is being awarded as a Fair and Open contract pursuant to N.J.S.A. 19:44A-20.5.

NOW, THEREFORE, BE IT RESOLVED BY THE MUNICIPAL COUNCIL OF THE CITY OF NEWARK, NEW JERSEY, THAT:

1. The Municipal Council hereby authorizes the Mayor and/or his designee, the Acting Director of the Department of Water and Sewer Utilities, to accept the lowest responsible bid submitted by Montana Construction Corp., Inc., on January 17, 2019, and execute Contract 13-WS2017 Phase-1(B) Sewer Cleaning and Rehabilitation, with Montana Construction Corp., Inc, 80 Contant Avenue, Lodi, New Jersey 07644, for the combined base bid and supplemental bid total amount not to exceed $6,743,122.00.

2. Attached hereto is a Certification of Funds from the Chief Financial Officer, which states that funds in the amount of $6,743,122.00, are available in the Water and Sewer Capital Budget under Business Unit NW044, Department ID 11G, Project 11SA0, Account 94710, Budget Ref: 2011 and which shall be filed along with the original resolution in the Office of the City Clerk.

3. There shall be no amendment or change to the contract without approval by the Newark Municipal Council.

4. There shall be no advance payment on this contract in accordance with N.J.S.A. 40A:5-16.

5. A fully executed copy of the contract shall be filed in the Office of the City Clerk, by the Department of Water and Sewer Utilities.

6. This contract was solicited and awarded pursuant to the fair and open procedures in accordance with the State Pay-to-Play Law (N.J.S.A. 19:44A-20.5), and pursuant to the provisions of the Local Public Contracts Law N.J.S.A. 40A:11-5(1)(a)(i), and is in compliance with the City's Contractor Pay-to-Play Reform Ordinance, R.O. 2:4-22C.

7. If required by State Law, the City Clerk shall provide the appropriate notice of the award of this contract to the State Comptroller no later than twenty (20) business days following such award, in accordance with N.J.S.A. 52:15C-10 and the Notice of the Office of the State Comptroller dated May 7, 2008.




STATEMENT

This resolution authorizes the Mayor and/or his designee, the Acting Director of the Department of Water and Sewer Utilities, to accept the lowest responsible bid submitted by Montana Construction Corp., Inc., on January 17, 2019, and execute Contract 13-WS2017 Phase-1(B) Sewer Cleaning and Rehabilitation, located at various locations in the City of Newark, with Montana Construction Corp., Inc., 80 Contant Avenue, Lodi, New Jersey 07644, for the combined base bid and supplemental bid total amount not to exceed $6,743,122.00.