File #: 18-0561    Version: Name: TE #25 Traffic Signal Optimization-Adaptive Signals McCarter Highway add'l funds
Type: Resolution Status: Adopted
File created: 4/13/2018 In control: Administration
On agenda: 6/20/2018 Final action: 6/20/2018
Title: Dept/ Agency: Administration/Office of Management and Budget Action: (X ) Ratifying (X) Authorizing ( ) Amending Type of Service: Temporary Emergency Appropriation Purpose: Traffic Signal Optimization/Adaptive Traffic Signals along McCarter Highway (Route 21) Project - additional funds (East Ward). Funding Source: North Jersey Transportation Planning Authority Appropriation Amount: $229,125.00 Budget Year: 2018 Contract Period: September 21, 2016 through September 20, 2019 Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( X ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Traffic Signal Optimization/Adaptive Signals along McCarter Highway: Total Award 965,265.00 Total Cash Match 236,502.00 Total Grant 1,201,767.00 Additional Award 229,125.00 Additional Cash Match 62,095.00 Total...
Sponsors: Augusto Amador, Gayle Chaneyfield Jenkins

Title

Dept/ Agency:  Administration/Office of Management and Budget

Action:  (X ) Ratifying     (X) Authorizing     (   ) Amending

Type of Service: Temporary Emergency Appropriation

Purpose: Traffic Signal Optimization/Adaptive Traffic Signals along McCarter Highway (Route 21) Project - additional funds (East Ward).

Funding Source: North Jersey Transportation Planning Authority

Appropriation Amount: $229,125.00

Budget Year:  2018

Contract Period:  September 21, 2016 through September 20, 2019     

Contract Basis: (   ) Bid   (   ) State Vendor   (   ) Prof.  Ser.   (   ) EUS  

(   ) Fair & Open   (   ) No Reportable Contributions   (   ) RFP   (   ) RFQ

(   ) Private Sale   ( X  ) Grant   (   ) Sub-recipient   (   ) n/a   

Additional Information:

Traffic Signal Optimization/Adaptive Signals along McCarter Highway:

Total Award

      965,265.00

Total Cash Match

      236,502.00

Total Grant

   1,201,767.00

Additional Award

      229,125.00

Additional Cash Match

        62,095.00

Total Additional Grant

      291,220.00

Grand Total Award

   1,194,390.00

Grand Total Cash Match

      298,597.00

Grand Total Grant

   1,492,987.00

Local Match of $62,095.00 from Unclassified Appropriations pending approval under Legistar File ID 18-0562

Funds accepted by Resolution 7R3-a adopted on May 23, 2018

Operating Agency: Department of Engineering

Two-Thirds vote of full membership required

body

 

TE-# 25

 

                      WHEREAS, an emergency has arisen in Special Item of Appropriation in the amount of $229,125.00 bringing total program resources to $1,194,390.00 for the continued provision of Traffic Signal Optimization/Adaptive Traffic Signals along McCarter Highway (Route 21) Project and no provision has been made in the 2018 Temporary Budget for the aforesaid purpose; and N.J.S.A. 40A:4-20 provides for the creation of an emergency appropriation for the purpose aforementioned; and

 

WHEREAS, by award letter dated March 5, 2018, the City of Newark accepted from North Jersey Transportation Planning Authority (NJTPA) in the amount of $229,125.00 for Traffic Signal Optimization/Adaptive Traffic Signals along McCarter Highway (Route 21) Project. A local match of $62,095.00 will be required for receipt and acceptance of this grant award and shall be provided from the 2018 Municipal Budget for a project total of $291,220.00. Traffic Signal Optimization/Adaptive Traffic Signals along McCarter Highway Grant (Route 21) Project commencing on September 21, 2016 and terminating September 20, 2019; and 

 

WHEREAS, N.J.S.A. 40A:4-20 provides that the Governing Body by a two-thirds vote may make temporary emergency appropriations for any purpose for which appropriations may lawfully be made for the period between the beginning of the current fiscal year and the date of the adoption of the budget for said year; and

 

WHEREAS, emergency appropriation adopted in 2018 pursuant to N.J.S.A. 40A:4-20 including this resolution total...$ 192,137,739.15

 

 

                     NOW, THEREFORE, BE IT RESOLVED BY THE MUNICIPAL COUNCIL OF THE CITY OF NEWARK, NEW JERSEY, THAT:

 

1.                     An emergency appropriation be and the same is hereby made for the following classification:  

 

Program                                                                                                                                                   Amount

 

  Traffic Signal Optimization/                                                                                    $229,125.00

  Adaptive Traffic Signals along

  McCarter Highway Grant (Route 21) Project

 

2.                     Said emergency appropriation shall be provided for in the 2018 budget.

 

3.                     A copy of this resolution shall be immediately filed with the Director of Local Government Services by the City Clerk of the City of Newark.

 

 

STATEMENT

 

This resolution establishes the additional appropriation in the amount of $229,125.00 for the Traffic Signal Optimization/Adaptive Traffic Signals along McCarter Highway (Route 21) Project. A local match of $62,095.00 shall be provided from the 2018 municipal budget, which brings the project total to $1,492,987.00. The project period commences on September 21, 2016 and terminating September 20, 2019. Funding has been provided by the North Jersey Transportation Planning Authority (NJTPA) and 2017 Matching Municipal funds. (East Ward)