Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution # Resolution # 7R12-a Adopted April 1, 2026
Purpose: To execute Contract Change Order #1 for Roof Replacement at the Archive Building, Chittenden Road Pumping Station, the City Hall Building, the JFK Recreation & Aquatic Center, and the S.W.A.T. Building - Contract 07-WS2026
Entity Name: 6 Brothers Contractors LLC
Entity Address: 41 Algonquin Avenue, Lincoln Park, New Jersey 07035
Contract Amount: Not to exceed $1,254,381.76
Funding Source: 2026 Budget/Department of Water and Sewer Utilities/ NW037-750-7505-71960 and NW038-800-8007-71970 Department of Public Works/Public Building 011-060-0604-71670 and CDBG Housing Community Development
Contract Period: Increase by 60 days for total 210 calendar days from the date of the written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A
Additional Information:
Resolution 7R12-a adopted on April 1, 2026, awarded a contract in an amount not to exceed $1,096,184.76 for a period of 150 calendar days from the date of the written Notice to Proceed to final completion.
Change Order #1 will increase the contract amount by $158,197.00 for a new total contract amount not to exceed $1,254,381.76 and increase time by 60 days for a period of 210 calendar days from the date of Notice to Proceed.
body
WHEREAS, 7R12-a adopted on April 1, 2026, authorized the Director of the Department of Water and Sewer Utilities to execute Contract 07-WS2026, Roof Replacement at the Archive Building, Chittenden Road Pumping Station, the City Hall Building, the JFK Recreation & Aquatic Center, and the S.W.A.T. Building, with 6 Brothers Contractors LLC (“6 Brothers”), 41 Algonquin Avenue, Lincoln Park, New Jersey 07035, in the amount of $1,096,184.76 for a period of 150 calendar days from the date of the written Notice to Proceed, in accordance with the Local Public Contracts Law, N.J.S.A. 4A:11-1 et seq: and
WHEREAS, a significant amount of time passed between the bid opening and the award of the contract and during that time the costs of various roofing materials increased significantly,6 Brothers has requested an adjustment in cost to compensate for the increase in material costs and increase time by 60 days to cover delays due to weather and other delays; and
WHEREAS, pursuant to N.J.A.C. 5:30-11 et eq. Contract No. 07-WS2026 is to be amended to include an increase in the contract amount by One Hundred Fifty-Eight Thousand, One Hundred Ninety-Seven Dollars and Zero Cents ($158,197.00) for a new contract amount of One Million Two Hundred Fifty-Four Thousand, Three Hundred Eighty-One Dollars and Seventy-Six Cents ($1,254,381.76) and increase time by 60 days for a total of 210 calendar days from the date of the written Notice to Proceed.
WHEREAS, the Department of Water and Sewer Utilities wishes to enter into and execute a Contract Change Order #1 to Contract 07-WS2026, Roof Replacement at the Archive Building, Chittenden Road Pumping Station, the City Hall Building, the JFK Recreation & Aquatic Center, and the S.W.A.T. Building, with 6 Brothers Contractors LLC, with an increase in the contract amount by One Hundred Fifty-Eight Thousand, One Hundred Ninety-Seven Dollars and Zero Cents ($158,197.00) for a new contract amount One Million Two Hundred Fifty-Four Thousand, Three Hundred Eighty-One Dollars and Seventy-Six Cents ($1,254,381.76) and increase time by 60 days for a total of 210 calendar days from the date of the written Notice to Proceed.
NOW, THEREFORE, BE IT RESOLVED BY THE MUNICIPAL COUNCIL OF THE CITY OF NEWARK, NEW JERSY, THAT:
1. The Mayor of the City of Newark and/or his designee, the Director of the Department of Water and Sewer Utilities, are authorized to enter into and execute Contract Change Order #1 for Roof Replacement at the Archive Building, Chittenden Road Pumping Station, the City Hall Building, the JFK Recreation & Aquatic Center, and the S.W.A.T. Building - Contract 07-WS2026, with 6 Brothers Contractors LLC, 41 Algonquin Avenue, Lincoln Park, New Jersey 07035, to increase the contract amount by One Hundred Fifty-Eight Thousand, One Hundred Ninety-Seven Dollars and Zero Cents ($158,197.00) bringing the contract amount to One Million Two Hundred Fifty-Four Thousand, Three Hundred Eighty-One Dollars and Seventy-Six Cents ($1,254,381.76) and increase time by 60 days for a total of 210 calendar days from the date of the written Notice to Proceed.
2. Attached hereto is a partial Certification of Funds from the Chief Financial Officer, which states that funds in the amount of One Thousand Dollars and Zero Cents ($1,000.00), are available in the Water and Sewer Utilities Capital Budget under NW037-750-7505-71960-B2026 and which shall be filed along with the original Resolution in the Office of the City Clerk.
3. A fully executed copy of the Change Order #1 shall be filed in the Office of the City Clerk by the Director of the Department of Water and Sewer Utilities.
4. If required by State Law, the City Clerk shall provide the appropriate notice of the award of this contract to the State Comptroller, no later than twenty (20) business days following such award, in accordance with N.J.S.A. 52:15C-10 and the Notice of the Office of the State Comptroller dated May 7, 2008.
STATEMENT
This Resolution amends and authorizes the Mayor of the City of Newark and/or his designee, the Director of the Department of Water and Sewer Utilities, to enter into and execute Contract Change Order #1 to Contract 07-WS2026, Roof Replacement at the Archive Building, Chittenden Road Pumping Station, the City Hall Building, the JFK Recreation & Aquatic Center, and the S.W.A.T. Building, with 6 Brothers Contractors LLC, increasing the contract amount by $158,197.00 for a total amount of $1,254,381.76, and increase time by 60 days for a total of 210 calendar days from the date of the written Notice to Proceed.