Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X ) Amending
Type of Service: Change Order #2/Amend Resolution 7R12-a(AS) adopted on September 5, 2019 and 7R12-b adopted on October 7, 2020
Purpose: Pequannock Watershed Dams/Reservoir Security Improvements - Phase 1 Contract 18-WS2018
Entity Name: Millennium Communications Group, Inc.
Entity Address: 11 Melanie Lane, Unit 13, East Hanover, New Jersey 07936
Contract Amount: Not to exceed $1,948,168.78
Funding Source: 2006 Budget/Department of Water and Sewer Capital Budget/NW041-W06-06S20-94710-B2006
Contract Period: 715 calendar days from the date of the issuance of a Notice to Proceed, with an end date of August 27, 2021
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Original Resolution 7R12-a(AS) adopted on September 5, 2019, awarded a contract in an amount not to exceed $1,948,168.78, for a period of sixty (60) calendar days for base bid items and 120 calendar days for supplemental bid items, from the date of the issuance of a Notice to Proceed.
Change Order #1 extended the completion time to 535 calendar days from the date of the issuance of a Notice to Proceed, with an end date of December 4, 2020.
Change Order #2 will extend the completion time to 715 days from the date of the issuance of a Notice to Proceed, with an end date of August 27, 2021.
body
WHEREAS, Resolution 7R12-a(AS) adopted on September 5, 2019, authorized the award of Contract 18-WS2018 to Millennium Communications Group, Inc., 11 Melanie Lane, Unit 13, East Hanover, New Jersey 07936, in the amount of $1,948,168.78 in accordance with the Local Public Contracts Law, N.J.S.A. 40A: 11-1 et seq.; and
WHEREAS, Change Order #1, by Resolution 7R12-b dated October 7, 2020, extended the...
Click here for full text