Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution Change Order #2 to Amend Resolution 7R12-a Adopted July 5, 2025
Purpose: To execute Contract Change Order #2 for the Rehabilitation of the Pequannock Aqueducts - Contract #14-WS2023
Entity Name: Hutton Construction, LLC
Entity Address: 41 Village Park Road, Cedar Grove, New Jersey 07009
Contract Amount: Increase the contract amount by $662,758.81 for a new contract amount not to exceed $14,876,037.22
Funding Source: 2023 Budget/Department of Water and Sewer Utilities/Business Unit: NW041, Dept. 23W, Div/Proj 23W00, Account #94710, Budget Ref. B2023
Contract Period: 1,102 calendar days from the date of the written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-a(as) adopted on June 5, 2024 awarded a contract in an amount not to exceed $13,119,347.00 for a period of 640 calendar days from the date of the written Notice to Proceed to final completion.
Change Order #1 Resolution adopted on July 2, 2025 increased the Contract amount by $1,093,931.41 for a new total contract amount not to exceed of $14,213,278.41, and will increase the contract period by 482 calendar days for a new completion period of 1,102 calendar days from the date of Notice to Proceed to final completion.
Change Order #2 will increase the contract amount by $662,758.81 for a new total contract amount not to exceed $14,876,037.22 for a period of 1,102 calendar days from the date of Notice to Proceed to final completion.
body
WHEREAS, 7R12-a(as) adopted on June 5, 2024, authorized the Director of the Department of Water and Sewer Utilities ("the Director") to execute Contract ...
Click here for full text