File #: 24-0168    Version: 1 Name: Close-out Change Order#1-Montana Phase-3(A)Sewer Cleaning and Rehabilitation- Contract 16-WS2017
Type: Resolution Status: Adopted
File created: 2/6/2024 In control: Water Sewer Utility
On agenda: 2/21/2024 Final action: 2/21/2024
Title: Dept/ Agency: Water and Sewer Utilities Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Final Quantities Change Order #1/Amend Resolution 7R12-b (AS) adopted on October 19, 2022 Purpose: To execute Contract Close-out Change Order #1 Phase-3(A) Sewer Cleaning and Rehabilitation- Contract 16-WS2017. Entity Name: Montana Construction Corporation, Inc. Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644 Contract Amount: Not to exceed $4,376,631.21 Funding Source: Capital Budget/Department of Water and Sewer Utilities Contract Period: 375 calendar days from the date of the written Notice to Proceed to final completion Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Resolution 7R12-b(AS) adopted on October 19, 2022 awarded a contract in an amount not to exce...
Sponsors: Council of the Whole
Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Final Quantities Change Order #1/Amend Resolution 7R12-b (AS) adopted on October 19, 2022
Purpose: To execute Contract Close-out Change Order #1 Phase-3(A) Sewer Cleaning and Rehabilitation- Contract 16-WS2017.
Entity Name: Montana Construction Corporation, Inc.
Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644
Contract Amount: Not to exceed $4,376,631.21
Funding Source: Capital Budget/Department of Water and Sewer Utilities
Contract Period: 375 calendar days from the date of the written Notice to Proceed to final completion
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-b(AS) adopted on October 19, 2022 awarded a contract in an amount not to exceed $4,329,230.00 for a period of (320) calendar days to final completion from the date of the written Notice to Proceed.

Contract Close-out Change Order #1 will increase the contract amount by $47,401.21 for a new total contract amount not to exceed $4,376,631.21 and increase the contract period by (55) calendar days for a new completion period of (375) calendar days from the date of the written Notice to Proceed to final completion.
body

WHEREAS, Resolution 7R12-b (as) adopted on October 19, 2022, authorized the award of Contract 16-WS2017, Phase-3 (A) Sewer Cleaning and Rehabilitation to Montana Construction Corporation, Inc., 80 Contant Avenue, Lodi, New Jersey 07644, in the amount of $4,329,230.00 for a period of (320) calendar days to final completion from the date of the written Notice to Proceed, in accordance with the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, the Contract 16-WS2017, was completed with an increase of $47,4...