File #: 18-0581    Version: 1 Name: Pequannock Water Treatment Plant Improvements Phase 2 - Change Order No. 2 - Allied Construction Group
Type: Resolution Status: Adopted
File created: 4/17/2018 In control: Water Sewer Utility
On agenda: 7/11/2018 Final action: 7/11/2018
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Change Order No. 2/Amend Resolution 7R1-d(AS)010616 and 7R12-c071217 Purpose: Execute Change Order No. 2 for Pequannock Water Treatment Plant Improvements Phase-2 Contract 06-WS2011 Entity Name: Allied Construction Group Inc. Entity Address: 499 Washington Road, Parlin, New Jersey 08859 Contract Amount: $5,253,213.00 Funding Source: Water and Sewer Utilities Capital Budget Contract Period: Final Completion extended by 466 days Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( X ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Change Order No. 2 will increase the original contract amount of $5,058,152.00, by $195,061.00, with a new contract total of $5,253,213.00, and extending the completion time by four hundr...
Sponsors: Council of the Whole
Related files: 17-0889, 22-1663, 15-2455, 20-0010
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Change Order No. 2/Amend Resolution 7R1-d(AS)010616 and 7R12-c071217
Purpose: Execute Change Order No. 2 for Pequannock Water Treatment Plant Improvements Phase-2 Contract 06-WS2011
Entity Name: Allied Construction Group Inc.
Entity Address: 499 Washington Road, Parlin, New Jersey 08859
Contract Amount: $5,253,213.00
Funding Source: Water and Sewer Utilities Capital Budget
Contract Period: Final Completion extended by 466 days
Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( X ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Change Order No. 2 will increase the original contract amount of $5,058,152.00, by $195,061.00, with a new contract total of $5,253,213.00, and extending the completion time by four hundred sixty-six (466) calendar days.
Original Resolution 7R1-d(AS) adopted on January 6, 2016
Change Order No. 1 Resolution 7R12-c adopted on July 12, 2017
body

WHEREAS, Resolution 7R1-d(AS) dated January 6, 2016 authorized the award of Contract 06-WS2011 to, Allied Construction Group Inc., 499 Washington Road, Parlin, New Jersey 08859 ("Allied"), in the amount of $4,877,000.00, in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, Resolution 7R12-c dated July 12, 2017 authorized the execution of Change Order No. 01 to Contract 06-WS2011 with Allied, increasing the Contract amount by $181,152.00 to a total resulting Contract amount of $5,058,152.00, and increasing contract completion time by two hundred fifty-seven (257) days, in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, the Department's SCADA integration was specified in the contract to be performed by the specified instrumentation integration ...

Click here for full text