Title
Dept/ Agency: Water & Sewer Utilities
Action:  (   ) Ratifying     (X) Authorizing     (X) Amending
Type of Service:  Change Order # 1/Amend Resolution # 7R12-b 070109
Purpose: Decrease the contract amount and extend the contract completion time by 47 days for the Phase VI(C) Sewer Rehabilitation
Entity Name:  Spiniello Companies
Entity Address:  354 Eisenhower Parkway, Livingston, NJ 07039
Decrease Contract Amount:  $1,112,653.50
New Contract Amount:  $4,882,521.50
Funding Source:  City of Newark Budget/ Water & Sewer Utilities
Contract Period:  290 calendar days from notice to proceed, extended by 47 calendar days
Contract Basis: (X) Bid   (   ) State Vendor   (   ) Prof.  Ser.   (   ) EUS   
(   ) Fair & Open   (   ) No Reportable Contributions   (   ) RFP   (   ) RFQ 
(   ) Private Sale   (   ) Grant   (   ) Sub-recipient   (   ) n/a
Additional Information:  N/A