Title: Dept/ Agency: Engineering Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order/Amend Resolution #: 7R4-c 060408 Purpose: Extend contract period and increase contract amount for the restoration of Boys Park Entity Name: Zenith Construction Services, Inc. Entity Address: 365 Thomas Street, Orange, NJ 07050 Additional Contract Amount: Not to exceed $203,528.00 Total Contract Amount: Not to exceed $1,221,168.00 Funding Source: City of Newark Budget/ Engineering Contract Period: August 8, 2008 - September 9, 2009 extended through June 30, 2011 Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: N/A Invitation: Engineering Director, September 7, 2011 Deferred 7R4-a 090811
Title
Dept/ Agency: Engineering
Action:  (X) Ratifying     (X) Authorizing     (X) Amending
Type of Service:  Change Order/Amend Resolution #: 7R4-c 060408
Purpose: Extend contract period and increase contract amount for the restoration of Boys Park
Entity Name:  Zenith Construction Services, Inc.
Entity Address:  365 Thomas Street, Orange, NJ 07050
Additional Contract Amount: Not to exceed $203,528.00
Total Contract Amount: Not to exceed $1,221,168.00
Funding Source: City of Newark Budget/ Engineering
Contract Period:  August 8, 2008 - September 9, 2009 extended through June 30, 2011
Contract Basis: (X) Bid   (   ) State Vendor   (   ) Prof.  Ser.   (   ) EUS   
(   ) Fair & Open   (   ) No Reportable Contributions   (   ) RFP   (   ) RFQ
(   ) Private Sale   (   ) Grant   (   ) Sub-recipient   (   ) n/a    
Additional Information:  N/A
Invitation: Engineering Director, September 7, 2011