File #: 23-1293    Version: 1 Name: Resolution Change Order# 2 Contract# 10-WS2020 - Spectraserv Inc.
Type: Resolution Status: Adopted
File created: 8/4/2023 In control: Water Sewer Utility
On agenda: 9/7/2023 Final action: 9/7/2023
Title: Dept/ Agency: Water and Sewer Utilities Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order #2/Amend Resolution 7R12-a(S)072021 and Resolution 7R12-a(S)121322 Purpose: To execute Change Order #2 Process and Operational Upgrades at the Pequannock Water Treatment Plant - Contract 10-WS2020. Entity Name: Spectraserv, Inc. Entity Address: 75 Jacobus Avenue, Kearny, New Jersey 07032 Contract Amount: Not to exceed $20,543,284.08 Funding Source: 2021Capital Budget/Department of Water and Sewer Utilities Utilities/NW041-21W-21W00-94710-B2021 Contract Period: 827 calendar days to final completion from the date of the issuance of a written Notice to Proceed Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Resolution 7R12-a(S)072021, awarded a contract in ...
Sponsors: Council of the Whole
Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order #2/Amend Resolution 7R12-a(S)072021 and Resolution 7R12-a(S)121322
Purpose: To execute Change Order #2 Process and Operational Upgrades at the Pequannock Water Treatment Plant - Contract 10-WS2020.
Entity Name: Spectraserv, Inc.
Entity Address: 75 Jacobus Avenue, Kearny, New Jersey 07032
Contract Amount: Not to exceed $20,543,284.08
Funding Source: 2021Capital Budget/Department of Water and Sewer Utilities Utilities/NW041-21W-21W00-94710-B2021
Contract Period: 827 calendar days to final completion from the date of the issuance of a written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-a(S)072021, awarded a contract in an amount not to exceed $19,789,000.00 for a period of 560 calendar days from the date of the issuance of a written Notice to Proceed.

Resolution 7R12-a(S)121322, authorized Change Order #1, which increased the contract amount by $357,075.07 for a total contract amount not to exceed $20,146,075.07 and increased the contract period by 130 calendar days for new completion contract period of 690 calendar days from the date of the issuance of a written Notice to Proceed.

Change Order #2 will increase the contract amount by $397,209.01 for a new total contract amount not to exceed $20,543,284.08, and increase the contract period by 137 calendar days for a new contract period of 827 calendar days from the date of the issuance of a written Notice to Proceed.
body

WHEREAS, Resolution 7R12-a(S) adopted on July 20, 2021, authorized the award of Contract 10-WS2020, Process and Operational Upgrades at the Pequannock Water Treatment Plant, to Spectraserv, Inc 7...