Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution # 7R12-b Adopted August 6, 2025
Purpose: To execute Contract Change Order #1 for Expansion of Filtration Building and Construction of Additional Filters 12 and 14 at the Pequannock Water Treatment Plant - Contract 18-WS2026 (Re-Bid)
Entity Name: Pact Two LLC
Entity Address: 554 Route 31, Ringoes, New Jersey 08551
Contract Amount: Not to exceed $12,700,000.00
Funding Source: Capital Budget/Department of Water and Sewer Utilities/ NW041-24W-24W00-94710-B2024
Contract Period: 365 calendar days from the date of the written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-b adopted on August 6 2025, awarded a contract in an amount not to exceed $12,700,000.00 for a period of 365 calendar days from the date of the written Notice to Proceed to final completion.
Change Order #1 will increase the contract period by 32 days for a new contract period of 397 days from the date of the written Notice to Proceed.
body
WHEREAS, 7R12-b adopted on August 6, 2025, authorized the Director of the Department of Water and Sewer Utilities to execute Contract 18-WS2025 Rebid, Expansion of Filtration Building and Construction of Additional Filters 12 and 4 at the Pequannock Water Treatment Plant, with Pact Two LLC ("Pact Two"), 554 Route 31, Ringoes, New Jersey 08551, in the amount of $12,700,000.00 for a period of 365 calendar days from the date of the written Notice to Proceed, in accordance with the Local Public Contracts Law, N.J.S.A. 4A:11-1 et seq: and
WHEREAS, due to lead-times associated with procurement of the butterfly valves impacting the critical path of the project, a non-c...