Title
Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X ) Amending
Type of Service: Professional Services Contract
Purpose: To execute Change Order/Amendment #1 to Contract #2017-02R PS, Providing Bid Documents, and Construction Administration for Rehabilitation of 13 Bridges, Various Locations in the City of Newark.
Entity Name: Remington & Vernick Engineers
Entity Address: One Harmon Plaza, Suite 210, Secaucus, New Jersey 07094
Contract Amount: Not to exceed $131,000.00
Funding Source: 2017 Budget/Department of Engineering/Business Unit: NW011; Department: 116; Div/Proj: 1167; Account #71930; Budget Year: B2017
Contract Period: Extending the original contract until completion of actual construction, pursuant to N.J.S.A. 40A: 11-15 (9)
Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS
(X ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Addition Information:
Original Resolution 7R3-b, adopted on April 24, 2018, authorized Contract #2017- 02R PS, Design, Providing Bid Documents, and Construction Administration for Rehabilitation of 13 Bridges, Various Locations in the City of Newark, New Jersey.
The Change Order/Amendment #1 to Contract #2017-02R PS will permit the distribution of contract fees for design and drafting of Bid Documents (not exceeding $71,000.00) and Construction Management fees (not exceeding $60,000.00), not to exceed $131,000.00.
No additional funding is required for this Change Order/Amendment #1.
body
WHEREAS, on April 24, 2018, the Municipal Council adopted Resolution 7R3-b authorizing the Director of the Department of Engineering to enter into and execute Contract #2017-02R PS, Design, Providing Bid Documents, and Construction Administration for Rehabilitation of 13 Bridges, Various Locations, City of Newark, New Jersey with Remington & Vernick Engineers, One Harmon Plaza...