File #: 09-0062    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 1/23/2009 In control: Engineering
On agenda: 2/4/2009 Final action: 2/4/2009
Title: Dept/ Agency: Engineering AUTHORIZING Type of Service: Contract # 29-2008 Purpose: Mildred Helms Park Retaining Wall Construction Entity Name: IBN Construction Address: 49 Hermon Street, Newark, NJ 0705 Contract Amount: Not to exceed $710,140.00 Contract Period: 120 days from notice to proceed Contract Basis: Bid X Prof. Ser. __ EUS__ Fair & Open__ Non-Fair & Open__ RFP__ RFQ __ Additional Comments: N/A Invitation: Engineering Director, February 3, 2009

Title

Dept/ Agency:  Engineering

AUTHORIZING

Type of Service:  Contract # 29-2008

Purpose: Mildred Helms Park Retaining Wall Construction

Entity Name:  IBN Construction

Address:  49 Hermon Street, Newark, NJ 0705

Contract Amount: Not to exceed $710,140.00

Contract Period:  120 days from notice to proceed

Contract Basis: Bid X  Prof.  Ser. __  EUS__   

Fair & Open__   Non-Fair & Open__   RFP__   RFQ __      

Additional Comments:  N/A

Invitation: Engineering Director, February 3, 2009