Skip to main content

 
File #: 25-1469    Version: 1 Name: Closeout Change order# 1 - 05-WS2022 - Montana
Type: Resolution Status: To Be Introduced
File created: 11/6/2025 In control: Water Sewer Utility
On agenda: 12/17/2025 Final action:
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Change Order/Amend Resolution # 7R12-b(as), adopted on November 2, 2022 Purpose: To execute Contract, Close out Change Order #1 Replacement of Fire Hydrants - Contract #05-WS2022 Entity Name: Montana Construction Corp., Inc. Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644 Contract Amount: Increase the contract amount by $21,205.00 for total not to exceed $2,196,360.00 Funding Source: 2025 Capital Budget/Department of Water and Sewer Utilities/NW037-750-7505-71960-B2025 Contract Period: 365 calendar days from the date of the issuance of a written Notice to Proceed until final completion Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Resolution 7R12-b(as)...
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Change Order/Amend Resolution # 7R12-b(as), adopted on November 2, 2022
Purpose: To execute Contract, Close out Change Order #1 Replacement of Fire Hydrants - Contract #05-WS2022
Entity Name: Montana Construction Corp., Inc.
Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644
Contract Amount: Increase the contract amount by $21,205.00 for total not to exceed $2,196,360.00
Funding Source: 2025 Capital Budget/Department of Water and Sewer Utilities/NW037-750-7505-71960-B2025
Contract Period: 365 calendar days from the date of the issuance of a written Notice to Proceed until final completion
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-b(as) adopted on November 2, 2022, awarded a contract in an amount not to exceed $2,175,155.00 for a period of 365 calendar days from the date of the issuance of a written Notice to Proceed until final completion.

Closeout Change Order #1 increases the contract amount by $21,205.00 for a new total contract amount not to exceed $2,196,360.00, with no extension to the contract period
body

WHEREAS, Resolution 7R12-b(as) adopted on November 2, 2022, authorized the award of Contract 05-WS2022, Replacement of Fire Hydrants, to Montana Construction Corp., Inc. 80 Contant Avenue, Lodi, New Jersey 07644, in the amount of $2,175,155.00 for a period of 365 calendar days to final completion from the date of the written Notice to Proceed, in accordance with the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, the Department of Water and Sewer Utilities determined that additional work related to the Replacement of Fire Hydrants services...

Click here for full text