File #: 15-0131    Version: 1 Name: McClellan St Design, Change Order # 2
Type: Resolution Status: Filed
File created: 1/20/2015 In control: Engineering
On agenda: 2/18/2015 Final action: 2/18/2015
Title: Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing ( X ) Amending Type of Service: Professional Services Contract Purpose: McClellan Street Underpass Roadway and Drainage Improvements Final Design, Change Order No. 2 Entity Name: Parsons Brinckerhoff, Inc. Entity Address: 2 Gateway Center, 18th Floor, Suite 1803, Newark, New Jersey 07102 Contract Amount: $0.00 Funding Source: N/A Contract Period: Extends the contract period until February 1, 2016 Contract Basis: ( ) Bid ( ) State Vendor ( X ) Prof. Ser. ( ) EUS ( ) Fair & Open ( X ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Addition Information: Amending Contract No. 06-2012PS extending the term of the contract, from January 16, 2013 through February 1, 2014 to January 16, 2013 through February 1, 2016. No increase in the original contract dollar amount of $1,091,849...
Sponsors: Mildred C. Crump, Gayle Chaneyfield Jenkins
Related files: 19-1726
Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing ( X ) Amending
Type of Service: Professional Services Contract
Purpose: McClellan Street Underpass Roadway and Drainage Improvements Final Design, Change Order No. 2
Entity Name: Parsons Brinckerhoff, Inc.
Entity Address: 2 Gateway Center, 18th Floor, Suite 1803, Newark, New Jersey 07102
Contract Amount: $0.00
Funding Source: N/A
Contract Period: Extends the contract period until February 1, 2016
Contract Basis: ( ) Bid ( ) State Vendor ( X ) Prof. Ser. ( ) EUS
( ) Fair & Open ( X ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Addition Information:
Amending Contract No. 06-2012PS extending the term of the contract, from January 16, 2013 through February 1, 2014 to January 16, 2013 through February 1, 2016. No increase in the original contract dollar amount of $1,091,849.92.

Resolution 7R4-C adopted May 18, 2011 (Original contract $3,188,600.00)
body

WHEREAS, Resolution 7R4-B, adopted October 17, 2012, authorized the Director of the Department of Engineering to accept the bid proposal and execute Contract No. 06-2012PS, McClellan Street Underpass Roadway and Drainage Improvements Final Design, with Parsons Brinckerhoff, Inc., 2 Gateway Center, 18th Floor, Suite 1803, Newark, New Jersey 07102 , for the amount of $1,091,849.92; and

WHEREAS, a 'Notice to Proceed' was issued dated January 16, 2013, specifying January 16, 2013 as the effective date of the contract, terminating on January 15, 2014; and

WHEREAS, Resolution 7R4-B, adopted March 5, 2014, authorized the Director of the Department of Engineering to issue and execute Change Order No. 1/Contract Amendment No. 1, to Contract #06-2012PS, McClellan Street Underpass Roadway and Drainage Improvements Final Design for a one (1) year extension o...

Click here for full text