File #: 16-0545    Version: 1 Name: Change Order #1 - Contract # 09-2014
Type: Resolution Status: Adopted
File created: 3/21/2016 In control: Engineering
On agenda: 7/19/2016 Final action: 8/3/2016
Title: Dept/ Agency: Engineering Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order/Amend Resolution Purpose: Complete unforeseen field conditions for Contract #09-2014 Mary Eliza Mahoney Health Center Dental Clinic Improvements at 110 William Street, Newark, New Jersey, 07102 Entity Name: Bismark Construction Corporation Entity Address: 207-209 Berkeley Avenue, Newark, New Jersey 07107 Contract Amount: $994,900.00 (with an increase of $100,900.37 for total contract amount of $1,095,800.37) Funding Source: City of Newark, Department of Health and Community Wellness Contract Period: Extend the term of the contract to February 27, 2015 through August 26, 2016 Contract Basis: (X) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Amending Contract #09-2014 amo...
Title
Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution
Purpose: Complete unforeseen field conditions for Contract #09-2014 Mary Eliza Mahoney Health Center Dental Clinic Improvements at 110 William Street, Newark, New Jersey, 07102
Entity Name: Bismark Construction Corporation
Entity Address: 207-209 Berkeley Avenue, Newark, New Jersey 07107
Contract Amount: $994,900.00 (with an increase of $100,900.37 for total contract amount of $1,095,800.37)
Funding Source: City of Newark, Department of Health and Community Wellness
Contract Period: Extend the term of the contract to February 27, 2015 through August 26, 2016
Contract Basis: (X) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Amending Contract #09-2014 amount from $994,900.00 to $1,095,800.37 (Increasing total amount by $100,900.37).
Resolution 7R4-C (A.S.), adopted January 21, 2015.


body

WHEREAS, Resolution 7R4-C (A.S.), adopted January 21, 2015, authorized the Director of the Department of Engineering, 920 Broad Street, Newark New Jersey 07102, to enter into and execute Contract #09-2014 Mary Eliza Mahoney Health Center Dental Clinic Improvements at 110 William Street, Newark, New Jersey, 07102 with Bismark Construction Corp., 207-209 Berkeley Avenue, Newark, New Jersey 07107, in the total bid amount of $994,900.00 ("Contract #09-2014"); and

WHEREAS, on February 27, 2015, the Department of Engineering issued a Notice To Proceed, specifying the contract term as one (1) year from that date; and

WHEREAS, due to unforeseen conditions discovered after the contract was awarded and interior demolition work had begun, including those necessary to obtain regulatory licensure approval for the health, s...