Title
Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution
Purpose: Complete unforeseen field conditions for Contract #09-2014 Mary Eliza Mahoney Health Center Dental Clinic Improvements at 110 William Street, Newark, New Jersey, 07102
Entity Name: Bismark Construction Corporation
Entity Address: 207-209 Berkeley Avenue, Newark, New Jersey 07107
Contract Amount: $994,900.00 (with an increase of $100,900.37 for total contract amount of $1,095,800.37)
Funding Source: City of Newark, Department of Health and Community Wellness
Contract Period: Extend the term of the contract to February 27, 2015 through August 26, 2016
Contract Basis: (X) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Amending Contract #09-2014 amount from $994,900.00 to $1,095,800.37 (Increasing total amount by $100,900.37).
Resolution 7R4-C (A.S.), adopted January 21, 2015.
body
WHEREAS, Resolution 7R4-C (A.S.), adopted January 21, 2015, authorized the Director of the Department of Engineering, 920 Broad Street, Newark New Jersey 07102, to enter into and execute Contract #09-2014 Mary Eliza Mahoney Health Center Dental Clinic Improvements at 110 William Street, Newark, New Jersey, 07102 with Bismark Construction Corp., 207-209 Berkeley Avenue, Newark, New Jersey 07107, in the total bid amount of $994,900.00 ("Contract #09-2014"); and
WHEREAS, on February 27, 2015, the Department of Engineering issued a Notice To Proceed, specifying the contract term as one (1) year from that date; and
WHEREAS, due to unforeseen conditions discovered after the contract was awarded and interior demolition work had begun, including those necessary to obtain regulatory licensure approval for the health, s...
Click here for full text