Skip to main content

 
File #: 25-0899    Version: 1 Name: Resolution Change Order#1 Contract 14-WS2023 - Hutton Construction LLC.
Type: Resolution Status: To Be Introduced
File created: 6/16/2025 In control: Water Sewer Utility
On agenda: 7/2/2025 Final action:
Title: Dept/ Agency: Water and Sewer Utilities Action: ( X ) Ratifying ( X ) Authorizing ( X ) Amending Type of Service: Change Order #1/Amend Resolution# 7R12-a(as) Adopted on June 5, 2024 Purpose: To execute Contract Change Order #1 for the rehabilitation of the Pequannock Aqueducts - Contract# 14-WS2023 Entity Name: Hutton Construction, LLC. Entity Address: 41 Village Park Road, Cedar Grove, New Jersey 07009 Contract Amount: Not to exceed $14,213,278.41 Funding Source: 2023 Budget/Department of Water and Sewer Utilities/Business Unit: NW041, Dept. 023W, Div./Proj. 23W00, Account #94710, Budget Ref. B2023 Contract Period: 1102 calendar days from the date of the written Notice to Proceed Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Resolution 7R12-a(as) adopted on June...
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( X ) Ratifying ( X ) Authorizing ( X ) Amending
Type of Service: Change Order #1/Amend Resolution# 7R12-a(as) Adopted on June 5, 2024
Purpose: To execute Contract Change Order #1 for the rehabilitation of the Pequannock Aqueducts - Contract# 14-WS2023
Entity Name: Hutton Construction, LLC.
Entity Address: 41 Village Park Road, Cedar Grove, New Jersey 07009
Contract Amount: Not to exceed $14,213,278.41
Funding Source: 2023 Budget/Department of Water and Sewer Utilities/Business Unit: NW041, Dept. 023W, Div./Proj. 23W00, Account #94710, Budget Ref. B2023
Contract Period: 1102 calendar days from the date of the written Notice to Proceed
Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-a(as) adopted on June 5, 2024 awarded a contract in an amount not to exceed $13,119,347.00 for a period of 620 calendar days from the date of the written Notice to Proceed to final completion.

Change Order #1 will increase the contract amount by $1,093,931.41 for a new total contract amount not to exceed $14,213,278.41, and will increase the contract period by 482 calendar days for a new completion period of 1,102 calendar days from the date of Notice to Proceed to final completion
body

WHEREAS, 7R12-a(as) adopted on June 5, 2024, the Director of the Department of Water and Sewer Utilities to execute Contract 14-WS2023, rehabilitation of the Pequannock Aqueducts, with Hutton Construction, LLC ("Hutton"), 41 Village Park Road, Cedar Grove, New Jersey 07009, in the amount of $13,119,347.00 for a period of 620 calendar days from the date of the written Notice to Proceed, in accordance with the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq; and
WHEREAS, during t...

Click here for full text