File #: 20-1690    Version: 1 Name: Change Order No. 1 to South Street and Adams Street Drainage Improvements Contract 12-WS2017
Type: Resolution Status: Adopted
File created: 12/23/2020 In control: Water Sewer Utility
On agenda: 1/21/2021 Final action: 1/21/2021
Title: Dept./ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing (X) Amending Type of Service: Bid Contract Purpose: To execute Change Order #1 for South Street and Adams Street Drainage Improvements - Contract 12-WS2017. Entity Name: CMS Construction, Inc. Entity Address: 521 North Avenue, Plainfield, New Jersey 07060 Total Contract Amount: Not to exceed $3,830,096.10 Funding Source: 2019 Budget/Department of Water and Sewer Utilities/NW044-19C-19C01-94710-B2019 Contract Period: 349 calendar days to final completion from the date of the written Notice to Proceed Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Resolution 7R12-a(AS) adopted on February 19, 2020 awarded a contract in an amount not to exceed $3,830,096.10 for a period of 219 calendar days ...
Sponsors: Council of the Whole
Related files: 22-0045
Title
Dept./ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Bid Contract
Purpose: To execute Change Order #1 for South Street and Adams Street Drainage Improvements - Contract 12-WS2017.
Entity Name: CMS Construction, Inc.
Entity Address: 521 North Avenue, Plainfield, New Jersey 07060
Total Contract Amount: Not to exceed $3,830,096.10
Funding Source: 2019 Budget/Department of Water and Sewer Utilities/NW044-19C-19C01-94710-B2019
Contract Period: 349 calendar days to final completion from the date of the written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-a(AS) adopted on February 19, 2020 awarded a contract in an amount not to exceed $3,830,096.10 for a period of 219 calendar days to final completion from the date of the written Notice to Proceed.

Change Order #1 will extend the original completion period by 130 calendar days with no change in contract amount.


body
WHEREAS, Resolution 7R12-a(as) dated February 19, 2020 authorized the award of Contract 12-WS2017 to, CMS Construction Inc, 521 North Avenue, Plainfield, New Jersey 07060, in the amount of $3,830,096.10, in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, during the course of the project, unexpected delays were encountered which necessitated an additional time of one hundred and thirty (130) calendar days required to complete the project; and

WHEREAS, the Contract 12-WS2017 is to be amended with no change in contract amount, and 130 calendar days to be added to the contract completion time; and

WHEREAS, the Department of Water and Sewer Utilities wishes to execute Change Order No.01 to Contract 12-WS2017 South Street and Adams ...