Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order #1/Amend Resolution #7R4-d(as) 070109
Purpose: Additional monies for materials to extend streetscape to cover Ferry Street and Union Street/McWhorter Street and inter-connect all the traffic signals for Contract #04-2009, Ferry Street Streetscape-Phase I-B
Entity Name: Berto Construction, Inc.
Entity Address: 625 Leesville Avenue, Rahway, NJ 07065
Original Contract Amount: $1,686,094.22
Additional Contract Amount: $318,015.27
Total Contract Amount: $2,004,109.49
Funding Source: City of Newark Budget/Engineering
Contract Period: 360 consecutive calendar days from Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information: N/A