File #: 17-0889    Version: 1 Name: Change Order No. 1 to Pequannock Water Treatment Plant Phase 2 - Allied Construction Group
Type: Resolution Status: Adopted
File created: 5/3/2017 In control: Water Sewer Utility
On agenda: 7/12/2017 Final action: 7/12/2017
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order No.01/Amend Resolution 7R1-d(AS)010616 Purpose: Execute Change Order No. 01 for Pequannock Water Treatment Plant Improvements Phase-2 Contract 06-WS2011 Entity Name: Allied Construction Group Inc. Entity Address: 499 Washington Road, Parlin, New Jersey 08859 Contract Amount: Original Contract Amount: $4,877,000.00, Increase for additional work: $181,152.00, Resulting Amended Contract Amount: $5,058,152.00 Funding Source: Water and Sewer Utilities Capital Budget Contract Period: 360 Calendar Days to Final Completion extended by 257 days for a total of 617 Calendar Days. Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Change Order No. 01 increases th...
Sponsors: Council of the Whole
Related files: 15-2455, 18-0581, 20-0010, 22-1663
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order No.01/Amend Resolution 7R1-d(AS)010616
Purpose: Execute Change Order No. 01 for Pequannock Water Treatment Plant Improvements Phase-2 Contract 06-WS2011
Entity Name: Allied Construction Group Inc.
Entity Address: 499 Washington Road, Parlin, New Jersey 08859
Contract Amount: Original Contract Amount: $4,877,000.00, Increase for additional work: $181,152.00, Resulting Amended Contract Amount: $5,058,152.00
Funding Source: Water and Sewer Utilities Capital Budget
Contract Period: 360 Calendar Days to Final Completion extended by 257 days for a total of 617 Calendar Days.
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Change Order No. 01 increases the total Contract amount by $181,152.00, and extends the completion time by 257 calendar days.
body

WHEREAS, Resolution 7R1-d(AS) dated, January 6, 2016, authorized the award of Contract 06-WS2011 to, Allied Construction Group Inc., 499 Washington Road, Parlin, New Jersey 08859 ("Allied"), in the amount of $4,877,000.00, in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, during the course of the project, Allied encountered unforeseen conditions which necessitated additional work in the amount of $181,152.00, and additional time of 257 calendar days needed to complete the additional work; and

WHEREAS, the Department of Water and Sewer Utilities wishes to amend Contract 06-WS2011 with a net amount of $181,152.00 added to the total contract amount and 257 calendar days added to the contract completion time; and

WHEREAS, the Department of Water and Sewer Utilities wishes to execute Change Order No.01 to Contract 06-WS2011 Pequannock Wa...