Title
Dept/ Agency: Administration/Division of Central Purchasing
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Extension of Emergency Contract #E2025-07
Purpose: To extend emergency contract #E2025-07 - Reconstruction Bay Floor-Fire Engine 5
Entity Name: Power Concrete Co., Inc.
Entity Address: 497 Raymond Boulevard Newark, NJ 07105
Contract Amount: Not to exceed $525,100.00
Funding Source: 2025 Budget/Department of Public Safety/NW051-G25-F25D0-72090-B2025
Contract Period: Extended an additional ninety (90) days from January 01, 2026, through March 31, 2026 or until completion of construction.
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient (X) n/a
Additional Information:
Emergency Contract #E2025-07 for the period of March 31, 2025 through June 30, 2025 was awarded for an amount not to exceed Five Hundred Twenty-Five Thousand One Hundred Dollars and Zero Cents ($525,100.00) for the Department of Public Safety Reconstruction of the Bay Floor-Fire Engine 5.
An extension was adopted on August 06, 2025 for the period from July 01, 2025 through September 30, 2025.
A further extension was adopted on November 06, 2025 for the period from October 01, 2025 through December 31, 2025.
This current Resolution of Emergency Contract #E2025-07 further extends the contract for an additional (90) days through March 31, 2026, or until the expected completion of the reconstruction project in February 2026.
body
WHEREAS, on March 31, 2025, the Department of Public Safety declared an emergency for immediate reconstruction of the floor bays that house fire apparatus Engine 5, located at 65 Congress Street, which among other issues, has been the subject of Public Employee Occupational Safety and Health ("PEOSH") violations, due to signs of deteriorated concrete and h...
Click here for full text