Legislation Details

File #: 26-1244    Version: 1 Name: Hutton Change Order #3 Rehabi Pequannock Aqueducts
Type: Resolution Status: To Be Introduced
File created: 8/25/2026 In control: Water Sewer Utility
On agenda: 9/9/2026 Final action:
Title: Dept/ Agency: Water and Sewer Utilities Action: (X) Ratifying (X) Authorizing (X ) Amending Type of Service: Change Order/Amend Resolution # 7R12-b Adopted April 15, 2026 Purpose: To execute Contract Change Order #3 for the Rehabilitation of the Pequannock Aqueducts – Contract #14-WS2023 Entity Name: Hutton Construction, LLC Entity Address: 41 Village Park Road, Cedar Grove, New Jersey 07009 Contract Amount: Increase of $857,191.99 for total contract amount not to exceed $15,733,229.21 Funding Source: 2023 Budget/Department of Water and Sewer Utilities/Business Unit: NW041, Dept. 23W, Div/Proj 23W00, Account #94710, Budget Ref. B2023 Contract Period: 1,102 calendar days from the date of the written Notice to Proceed Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A Additional Information: Resolut...
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X ) Amending
Type of Service: Change Order/Amend Resolution # 7R12-b Adopted April 15, 2026
Purpose: To execute Contract Change Order #3 for the Rehabilitation of the Pequannock Aqueducts – Contract #14-WS2023
Entity Name: Hutton Construction, LLC
Entity Address: 41 Village Park Road, Cedar Grove, New Jersey 07009
Contract Amount: Increase of $857,191.99 for total contract amount not to exceed $15,733,229.21
Funding Source: 2023 Budget/Department of Water and Sewer Utilities/Business Unit: NW041, Dept. 23W, Div/Proj 23W00, Account #94710, Budget Ref. B2023
Contract Period: 1,102 calendar days from the date of the written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A
Additional Information:
Resolution 7R12-a(as) adopted on June 5, 2024 awarded a contract in an amount not to exceed $13,119,347.00 for a period of 640 calendar days from the date of the written Notice to Proceed to final completion.

Change Order #1 Resolution 7R12-a adopted on July 2, 2025 increased the contract amount by $1,093,931.41 for a new total contract amount not to exceed of $14,213,278.41, and will increase the contract period by 482 calendar days for a new completion period of 1,102 calendar days from the date of Notice to Proceed to final completion.

Change Order #2 Resolution 7R12-b adopted on April 15, 2026 increased the contract amount by $662,758.81 for a new total contract amount not to exceed $14,876,037.22 for a period of 1,102 calendar days from the date of Notice to Proceed to final completion.

Change Order #3 will increase the contract amount by $857,191.99 for a new total contract amount not to exceed $15,733,229.21 for a period of 1,102 calendar days from the date of Notice to P...

Click here for full text