File #: 13-2100    Version: 1 Name: Granada Construction Corp. - Change Order # 1, Various Streets (11 Locations) (2012-2014)
Type: Resolution Status: Filed
File created: 10/30/2013 In control: Engineering
On agenda: 12/18/2013 Final action: 12/18/2013
Title: Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Change Order/Amend Resolution Purpose: To amend Contract No. 11-2011, Various Streets (11 Locations) - 2011 Project Entity Name: Granada Construction Corp Entity Address: 147 Thomas Street, Newark, New Jersey 07114 Contract Amount: $2,169,182.05 Funding Source: Hess Trust Contract Period: Extend contract termination date to June 1, 2014 Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Contract Period: November 28, 2012 through November 28, 2013, now extended through June 1, 2014 Contract amount increased by $100,000.
Related files: 12-1388
Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Change Order/Amend Resolution
Purpose: To amend Contract No. 11-2011, Various Streets (11 Locations) - 2011 Project
Entity Name: Granada Construction Corp
Entity Address: 147 Thomas Street, Newark, New Jersey 07114
Contract Amount: $2,169,182.05
Funding Source: Hess Trust
Contract Period: Extend contract termination date to June 1, 2014
Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Contract Period: November 28, 2012 through November 28, 2013, now extended through June 1, 2014
Contract amount increased by $100,000.
body

WHEREAS, Resolution No. 7R4-A, adopted September 6, 2012, authorized the Director of the Department of Engineering to accept the bid proposal and execute Contract No. 11-2011, Various Streets (11 Locations) - 2011 Project, with Granada Construction Corp., 147 Thomas Street, Newark, New Jersey 07114, for the amount of $2,069,182.05; and

WHEREAS, the Department of Engineering needs to increase existing quantities for drainage repairs, concrete curb, asphalt and striping due to unforeseen conditions. These additional work items are necessary in order to complete the ongoing work along the streets under the original contract; and

WHEREAS, the Director of the Department of Engineering has certified that the change order is allowed pursuant to the regulations governing construction contract change orders, more specifically, N.J.A.C. 5:30-11.1, et seq., and do not constitute a material expansion in the size, nature or scope of the Project and the extra work cannot be reasonably effectuated by a separately bid contract without unduly disrupting the...