Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution 7R12-a adopted on April 5, 2023 and 7R12-a(AS) adopted on December 15, 2021
Purpose: To execute Contract Change Order #2 for Valley Road Corrosion Control Chemical Feed System - Phase II Improvements - Contract 10-WS2021 (Re-bid).
Entity Name: Underground Utilities Corporation
Entity Address: 711 Commerce Road, Linden, New Jersey 07036
Contract Amount: Not to exceed $1,344,123.00
Funding Source: 2021 Budget/Department of Water and Sewer Utilities/Capital Budget/NW037-750-7505-71960-B2021
Contract Period: 759 calendar days from the date of a written Notice to Proceed to final completion on February 29, 2024
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-a(AS) adopted on December 15, 2021 awarded a contract in an amount not to exceed $1,344,123.00, for a period of (260) calendar days to substantial and final completion from the date of a written Notice to Proceed.
Resolution 7R12-a adopted on April 5, 2023 - Change Order #1 extended the completion time by (180) for a new completion period of (440) calendar days from the date of a written Notice to Proceed to final completion on June 25, 2023.
Change Order #2 will extend the completion time by (319) for a new completion period of (759) calendar days from the date of a written Notice to Proceed to final completion on February 29, 2024.
body
WHEREAS, Resolution 7R12-a adopted on December 15, 2021, authorized the award of Contract 10-WS2021 (Re-bid) to Underground Utilities Corporation, Inc., 711 Commerce Road, Linden New Jersey 07036, in the amount of $1,344,123.00 for a period of 260 calendar days to final completion from the date of writ...
Click here for full text