File #: 24-0169    Version: 1 Name: Close-out Change Order#1-Spiniello Phase-3(B)Sewer Cleaning and Rehabilitation-Contract 17-WS2017
Type: Resolution Status: Adopted
File created: 2/6/2024 In control: Water Sewer Utility
On agenda: 2/21/2024 Final action: 2/21/2024
Title: Dept/ Agency: Water and Sewer Utilities Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Final Quantities Change Order #1/Amend Resolution 7R12-a (AS) adopted on October 19, 2022 Purpose: To execute Contract Close-out Change Order #1 Phase-3(B) Sewer Cleaning and Rehabilitation- Contract 17-WS2017. Entity Name: Spiniello Companies Entity Address: 354 Eisenhower Parkway, Livingston, New Jersey 07039 Contract Amount: Not to exceed $6,062,533.88 Funding Source: Capital Budget/Department of Water and Sewer Utilities Contract Period: 365 calendar days from the date of the written Notice to Proceed to final completion Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Resolution 7R12-a(AS) adopted on October 19, 2022 awarded a contract in an amount not to exceed $4,823,...
Sponsors: Council of the Whole
Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Final Quantities Change Order #1/Amend Resolution 7R12-a (AS) adopted on October 19, 2022
Purpose: To execute Contract Close-out Change Order #1 Phase-3(B) Sewer Cleaning and Rehabilitation- Contract 17-WS2017.
Entity Name: Spiniello Companies
Entity Address: 354 Eisenhower Parkway, Livingston, New Jersey 07039
Contract Amount: Not to exceed $6,062,533.88
Funding Source: Capital Budget/Department of Water and Sewer Utilities
Contract Period: 365 calendar days from the date of the written Notice to Proceed to final completion
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-a(AS) adopted on October 19, 2022 awarded a contract in an amount not to exceed $4,823,300.00 for a period of (320) calendar days to final completion from the date of the written Notice to Proceed.

Contract Close-out Change Order #1 will increase the contract amount by $1,239,233.88 for a new total contract amount not to exceed $6,062,533.88 and increase the contract period by (45) calendar days for a new completion period of (365) calendar days from the date of the written Notice to Proceed to final completion.
body

WHEREAS, Resolution 7R12-a (as) adopted on October 19, 2022, authorized the award of Contract 17-WS2017, Phase-3 (B) Sewer Cleaning and Rehabilitation to Spiniello Companies, 354 Eisenhower Parkway, Livingston, New Jersey 07039, in the amount of $4,823,300.00 for a period of (320) calendar days to final completion from the date of the written Notice to Proceed, in accordance with the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, the Contract 17-WS2017, was completed with an increase of $1,239,233.88 due to...