File #: 22-0514    Version: 1 Name: Michael Baker International - Amendment #1 to Engineering Services for Construction Phase of South Street and Adam Street Area Drainage Improvements
Type: Resolution Status: Adopted
File created: 3/30/2022 In control: Water Sewer Utility
On agenda: 7/13/2022 Final action: 7/13/2022
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing (X) Amending Type of Service: Professional Services Contract Purpose: Amendment #1 to Engineering Services for Construction Phase of South Street and Adam Street Area Drainage Improvements. Entity Name: Michael Baker International, Inc. Entity Address: 100 Airside Drive, Moon Township, Pennsylvania 15108 Contract Amount: Not to exceed $783,037.42 Funding Source: 2022 Budget/Department of Water and Sewer Utilities/NW038-800-8003-71280 B2022 Contract Period: Until Project completion pursuant to N.J.S.A. 40A: 11-15(9) Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS ( ) Fair & Open (X) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A Additional Information: Resolution 7R12-b(S/AS) adopted on May 30, 2018, awarded a contract in the amount of $517,430.09 until project completion pursuant to N.J...
Sponsors: Council of the Whole
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Professional Services Contract
Purpose: Amendment #1 to Engineering Services for Construction Phase of South Street and Adam Street Area Drainage Improvements.
Entity Name: Michael Baker International, Inc.
Entity Address: 100 Airside Drive, Moon Township, Pennsylvania 15108
Contract Amount: Not to exceed $783,037.42
Funding Source: 2022 Budget/Department of Water and Sewer Utilities/NW038-800-8003-71280 B2022
Contract Period: Until Project completion pursuant to N.J.S.A. 40A: 11-15(9)
Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS
( ) Fair & Open (X) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A
Additional Information:
Resolution 7R12-b(S/AS) adopted on May 30, 2018, awarded a contract in the amount of $517,430.09 until project completion pursuant to N.J.S.A. 40A: 11-15(9) .
This Amendment #1 will increase the contract amount by $265,607.33 for a new total contract amount of $783,037.42.
body

WHEREAS, Resolution 7R12-b(s/as) adopted on May 30, 2018, authorized the Director of the Department of Water and Sewer Utilities to execute a contract with Michael Baker International, Inc., 100 Airside Drive, Moon Township, Pennsylvania 15108, to provide Engineering Services for Construction Phase of South Street and Adam Street Area Drainage Improvements, in an amount not to exceed $517,430.09 for a contract time period until project completion per N.J.S.A. 40A:11-15(9); and

WHEREAS, the City of Newark is currently involved in the construction of the South and Adam Street Area Drainage Improvements contract with the construction managerial services of Michael Baker International, Inc. The construction contract has recently expanded, which requires extended construction management services and design s...

Click here for full text