File #: 24-1075    Version: 1 Name: Newark Downtown Connector- Extension Request
Type: Resolution Status: Adopted
File created: 7/29/2024 In control: Engineering
On agenda: 9/5/2024 Final action: 9/5/2024
Title: Dept/ Agency: Engineering Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Amending Resolution 7R3-a adopted on August 3, 2022, Accepting Grant Purpose: To amend the grant award amount and request an extension from NJDOT to allow the City of Newark additional time to award a contract for construction of the Bikeway Program for the Newark Downtown Connector Project. Entity Name: New Jersey Department of Transportation (NJDOT) Entity Address: P.O. Box 600, Trenton, New Jersey 08625 Grant Amount: $379,000.00 Total Project Cost: $379,000.00 City Contribution: $0.00 Other Funding Source/Amount: Not Applicable Grant Period: December 12, 2022 through December 11, 2024, with an extension request to June 12, 2025 Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale (X) Grant ( ) Sub-recipient ( ...
Title
Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Amending Resolution 7R3-a adopted on August 3, 2022, Accepting Grant
Purpose: To amend the grant award amount and request an extension from NJDOT to allow the City of Newark additional time to award a contract for construction of the Bikeway Program for the Newark Downtown Connector Project.
Entity Name: New Jersey Department of Transportation (NJDOT)
Entity Address: P.O. Box 600, Trenton, New Jersey 08625
Grant Amount: $379,000.00
Total Project Cost: $379,000.00
City Contribution: $0.00
Other Funding Source/Amount: Not Applicable
Grant Period: December 12, 2022 through December 11, 2024, with an extension request to June 12, 2025
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale (X) Grant ( ) Sub-recipient ( ) n/a
List of Property: (if applicable)
(Address/Block/Lot/Ward/Site Known As)
Additional Information:
This Resolution ratifies and authorizes the City of Newark to amend the grant award amount and request an extension from NJDOT to allow the City of Newark additional time to award a contract for construction of the Bikeway Program for the Newark Downtown Connector from December 11, 2024 through June 12, 2025.
body

WHEREAS, the State of New Jersey Department of Transportation (NJDOT) FY 2023 Bikeways State Aid Program provides municipalities with grant funding for bicycle lane projects; and

WHEREAS, on July 1, 2022, the Director of the Department of Engineering, on behalf of the City of Newark (the "City"), submitted an application to NJDOT requesting grant funding from the Bikeway State Aid Program for the Newark Downtown Connector within the City of Newark, identified as application BIKE-2023 Newark Downtown Connector ...