File #: 19-0036    Version: 1 Name: Change Order #1 Perform Maintenance and Repairs of the Chlorine System at the Newark's Pequannock Water Treatment Plant
Type: Resolution Status: Adopted
File created: 1/9/2019 In control: Water Sewer Utility
On agenda: 6/6/2019 Final action: 6/6/2019
Title: Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order/Amend Resolution 7R12-b adopted on September 7, 2017 Purpose: Change Order #1, Perform Maintenance and Repairs of the Chlorine System at Newark's Pequannock Water Treatment Plant Entity Name: Ray Palmer Associates, Inc. Entity Address: 95 King Street, Dover, New Jersey 07801 Contract Amount: Not to exceed $120,000.00 Funding Source: 2019 Budget/Department of Water and Sewer Utilities/NW037-750-7502-71770-B2019 Contract Period: Two (2) years from the issuance of a Notice to Proceed Contract Basis: (X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Original Resolution 7R12-b adopted on September 7, 2017 with a contract amount not to exceed $100,000.00. Change Order #1 will i...
Sponsors: Council of the Whole
Related files: 17-1319
Title
Dept/ Agency: Water and Sewer Utilities
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution 7R12-b adopted on September 7, 2017
Purpose: Change Order #1, Perform Maintenance and Repairs of the Chlorine System at Newark's Pequannock Water Treatment Plant
Entity Name: Ray Palmer Associates, Inc.
Entity Address: 95 King Street, Dover, New Jersey 07801
Contract Amount: Not to exceed $120,000.00
Funding Source: 2019 Budget/Department of Water and Sewer Utilities/NW037-750-7502-71770-B2019
Contract Period: Two (2) years from the issuance of a Notice to Proceed
Contract Basis: (X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Original Resolution 7R12-b adopted on September 7, 2017 with a contract amount not to exceed $100,000.00.
Change Order #1 will increase the contract by $20,000.00 for a new contract amount not to exceed $120,000.00.
body

WHEREAS, Resolution # 7R12-b 090717, adopted on September 7, 2017 authorized the performance of preventative maintenance and repairs of the Chlorine System at the City of Newark's Pequannock Water Treatment Plant to Ray Palmer Associates, Inc., 95 King Street, Dover, New Jersey 07801, in an amount not to exceed $100,000.00, in accordance with Local Public Contracts Law N.J.S.A. 40A:11-1 et. seq.; and

WHEREAS, as a result of unforeseen conditions which necessitated additional work due the Treatment Plant's aging chlorine infrastructure, the additional work required at the Valley Road Re-Chlorination Station and the Pequannock Water Treatment Plant are necessary to successfully complete the repairs; and

WHEREAS, the requested additional work for the contract increases the total contract amount by Twenty Thousand Dollars and Zero Cents ($20,000.00), and this amount i...