Title: Dept/ Agency: Engineering Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order/Amend Resolution Purpose: Change Order #4 - McClellan Street Underpass Roadway and Drainage Improvements Final Design Entity Name: WSP USA, Inc. (formerly known as Parsons Brinckerhoff, Inc.) Entity Address: One Penn Plaza, New York, New York 10119 Contract Amount: Not to exceed $1,278,519.92 Funding Source: Federal Grant modification administered by NJDOT Contract Period: Extended through February 1, 2022 Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Resolution 7R4-b adopted on October 17, 2012, awarded a contract in an amount not to exceed $1,091,849.92 for the period of 365 consecutive calendar days from the date of the issuance of a formal Notice to Proc...
Sponsors: John Sharpe James, Eddie Osborne
Title
Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution
Purpose: Change Order #4 - McClellan Street Underpass Roadway and Drainage Improvements Final Design
Entity Name: WSP USA, Inc. (formerly known as Parsons Brinckerhoff, Inc.)
Entity Address: One Penn Plaza, New York, New York 10119
Contract Amount: Not to exceed $1,278,519.92
Funding Source: Federal Grant modification administered by NJDOT
Contract Period: Extended through February 1, 2022
Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R4-b adopted on October 17, 2012, awarded a contract in an amount not to exceed $1,091,849.92 for the period of 365 consecutive calendar days from the date of the issuance of a formal Notice to Proceed - January 15, 2014.

Change Orders #1, 2, and 3 (Resolution 7R4-b adopted on March 5, 2014, Resolution 7R4-a adopted on February 18, 2015, and Resolution 7R4-b adopted on March 2, 2016) extended the ending date of original contract period to February 1, 2015, February 1, 2016 and February 1, 2017, respectively.

Change Order # 4 will extend the end date of original contract to February 1, 2022, and an increase the contract amount by $186,670.00 for a total contract amount not to exceed $1,278,519.92.
body

WHEREAS, Resolution 7R4-b, adopted on October 17, 2012, authorized the Director of the Department of Engineering ("to accept the bid proposal and execute Contract #06-2012PS, McClellan Street Underpass Roadway and Drainage Improvements Final Design, with Parsons Brinckerhoff, Inc., 2 Gateway Center, 18th Floor, Suite 1803, Newark, New Jersey 07102, for the amount of $1,091,849.92; and

WHEREAS, the Department of Engineering issued an initial 'Notice to Pr...