File #: 24-1166    Version: 1 Name: TV-23 Morris Canal Bikeway Project - Extension Request
Type: Resolution Status: Adopted
File created: 8/20/2024 In control: Engineering
On agenda: 9/5/2024 Final action: 9/5/2024
Title: Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing (X) Amending Type of Service: Amending Resolution 7R3-b adopted on August 3, 2022, accepting grant Purpose: To request an extension from New Jersey Department of Transportation (NJDOT) to allow the City of Newark additional time to award a contract for construction of the LA-2023 TV Newark City Newark Morris Canal Bikeway Project. Entity Name: New Jersey Department of Transportation (NJDOT) Entity Address: P.O. Box 600, Trenton, New Jersey 08625 Grant Amount: $470,000.00 Total Project Cost: Not Applicable City Contribution: $0.00 Other Funding Source/Amount: Grant Period: December 12, 2022 through December 11, 2024, requesting an extension to June 12, 2025 Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale (X) Grant ( ) Sub-recipient ( ) n/a List of Proper...
Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing (X) Amending
Type of Service: Amending Resolution 7R3-b adopted on August 3, 2022, accepting grant
Purpose: To request an extension from New Jersey Department of Transportation (NJDOT) to allow the City of Newark additional time to award a contract for construction of the LA-2023 TV Newark City Newark Morris Canal Bikeway Project.
Entity Name: New Jersey Department of Transportation (NJDOT)
Entity Address: P.O. Box 600, Trenton, New Jersey 08625
Grant Amount: $470,000.00
Total Project Cost: Not Applicable
City Contribution: $0.00
Other Funding Source/Amount:
Grant Period: December 12, 2022 through December 11, 2024, requesting an extension to June 12, 2025
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale (X) Grant ( ) Sub-recipient ( ) n/a
List of Property: (if applicable)
(Address/Block/Lot/Ward/Site Known As)
Additional Information:
This Resolution authorizes the City of Newark to request a time extension from NJDOT to allow the City of Newark additional time to award a contract for construction of the Transit Village Program for LA-2023 TV Newark City Newark Morris Canal Bikeway Project from December 11, 2024 through June 12, 2025.
body

WHEREAS, the State of New Jersey Department of Transportation (NJDOT) FY-2023 Transit Village Grant Program for LA-2023 TV provides Municipalities with grant funding for bicycle lane projects; and

WHEREAS, on July 1, 2022, the Acting Director of the Department of Engineering, on behalf of the City of Newark (the "City"), submitted an application to NJDOT requesting grant funding from the NJDOT FY-2023 Transit Village Grant Program for construction of the Newark Morris Canal Bikeway Project, identified as LA-2023 TV Newark City Newark M...