Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order #4/Amend Resolution 7R12-a(AS) adopted on September 5, 2019 and 7R12-b adopted on October 7, 2020 and 7R12-b adopted on June 2, 2021 and 7R12-a adopted December 1, 2021
Purpose: To provide Pequannock Watershed Dams/Reservoir Security Improvements - Phase 1, Contract 18-WS2018.
Entity Name: Millennium Communications Group, Inc.
Entity Address: 11 Melanie Lane, Unit 13, East Hanover, New Jersey 07936
Contract Amount: Not to exceed $1,948,168.25
Funding Source: Capital Budget/Department of Water and Sewer Utilities/NW041-W06-06S20-94710-B2006
Contract Period: 1,147 calendar days from the date of an issuance of a written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Original Resolution 7R12-a(AS) adopted on September 5, 2019 awarded a contract in an amount not to exceed $1,948,168.78, for a period of sixty (60) calendar days for base bid items and (120) calendar days for supplemental bid items, from the date of the issuance of a written Notice to Proceed.
Resolution 7R12-b adopted on October 7, 2020 - Change Order #1 extended the completion time to (535) calendar days from the date of the issuance of a written Notice to Proceed, with an end date of December 4, 2020.
Resolution 7R12-b adopted on June 2, 2021 - Change Order #2 extended the completion time to (715) days from the date of the issuance of a written Notice to Proceed, with an end date of August 27, 2021.
Resolution 7R12-a adopted on December 1, 2021 - Change Order #3 changed contract specifications at no extra cost and no change in the contract time period.
Change Order #4 will reduce the contract amount by $0.53 for a new total contract amount not ...