Title: Dept/ Agency: Water and Sewer Utilities Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order/Amend Resolution 7R12-c(AS) adopted on December 18, 2019 Purpose: Change Order #1 to Pequannock Screen Building Spray Wash Replacement - Contract 21-WS2009. Entity Name: Rapid Pump and Meter Service Company, Incorporated Entity Address: 285 Straight Street, P.O. Box AY, Paterson, New Jersey 07501 Contract Amount: Not to exceed $323,790.00 Funding Source: 2019 Budget/Department of Water and Sewer Utilities/NW037-750-7505-71960-B2019 Contract Period: 150 calendar days from date of the issuance of a Notice to Proceed, extended by 120 calendar days for a total of 270 calendar days from the date of the issuance of a Notice to Proceed Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) ...
Sponsors: Council of the Whole
Title
Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Change Order/Amend Resolution 7R12-c(AS) adopted on December 18, 2019
Purpose: Change Order #1 to Pequannock Screen Building Spray Wash Replacement - Contract 21-WS2009.
Entity Name: Rapid Pump and Meter Service Company, Incorporated
Entity Address: 285 Straight Street, P.O. Box AY, Paterson, New Jersey 07501
Contract Amount: Not to exceed $323,790.00
Funding Source: 2019 Budget/Department of Water and Sewer Utilities/NW037-750-7505-71960-B2019
Contract Period: 150 calendar days from date of the issuance of a Notice to Proceed, extended by 120 calendar days for a total of 270 calendar days from the date of the issuance of a Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A
Additional Information:
Original Resolution 7R12-c(AS) adopted on December 18, 2019, awarded a contract in an amount not to exceed $323,790.00, for a period of 150 calendar days from the date of the issuance of a Notice to Proceed.

Change Order #1 will extend the completion time by 120 calendar days from the date of the issuance of a Notice to Proceed, with an end date of November 20, 2020.
body

WHEREAS, Resolution 7R12-c(AS) adopted on December 18, 2019, authorized the award of Contract 21-WS2009 to Rapid Pump and Meter Service Company, Incorporated, 285 Straight Street, P.O. Box AY, Paterson, New Jersey 07501, in the amount of Three Hundred Twenty-Three Thousand Seven Hundred Ninety Dollars and Zero Cents ($323,790.00) in accordance with the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq.: and

WHEREAS, due to the Covid-19 pandemic, time delays occurred in the shipping and delivery of the spray wash pump equipment. Also, changes were requested of...