Title: Dept/ Agency: Administration/Division of Central Purchasing Action: (X) Ratifying (X) Authorizing (X) Amending Type of Service: Extension of Emergency Contract #E2023-13 Purpose: To provide for the extension of the contract period of the Emergency Contract #E2023-13 to provide repairs at the Clinton Reservoir Dam - Downstream Spillway Discharge Channel. Entity Name: Hutton Construction, LLC Entity Address: 41 Village Park Road, Cedar Grove, New Jersey 07009 Contract Amount: $0.00 Funding Source: 2023 Budget/Department of Water and Sewer Utilities/NW041-16W-94710-B22016 Contract Period: Extended an additional six (6) months, from March 1 2024 through August 31, 2024 Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient (x ) n/a Additional Information: Contract #2023-13 was awarded to Hutton Construction, L...
Sponsors: Council of the Whole
Title
Dept/ Agency: Administration/Division of Central Purchasing
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Extension of Emergency Contract #E2023-13
Purpose: To provide for the extension of the contract period of the Emergency Contract #E2023-13 to provide repairs at the Clinton Reservoir Dam - Downstream Spillway Discharge Channel.
Entity Name: Hutton Construction, LLC
Entity Address: 41 Village Park Road, Cedar Grove, New Jersey 07009
Contract Amount: $0.00
Funding Source: 2023 Budget/Department of Water and Sewer Utilities/NW041-16W-94710-B22016
Contract Period: Extended an additional six (6) months, from March 1 2024 through August 31, 2024
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient (x ) n/a
Additional Information:
Contract #2023-13 was awarded to Hutton Construction, LLC, in an amount not exceeding $367,419.00 for the period of December 1, 2023, through February 29, 2024, for the Department of Water and Sewer Utilities.

This Resolution provides for a 1st extension and amendment of Emergency Contract #E2023-13 extending the contract period through August 31, 2024 with no increase to the contract amount. All other terms of the original Emergency Declaration will remain the same.
body

WHEREAS, on November 6, 2023, the Dam Inspector, GZA Geo Environmental, Inc. , informed the Department of Water and Sewer Utilities ("the Department") of the need for immediate repairs to the concrete sill downstream of the spillway at the Clinton Reservoir Dam; and

WHEREAS, as a result of that letter, the Director of the Department requested a declaration of emergency for the repairs; and

WHEREAS, on December 1, 2023, pursuant to N.J.S.A. 40A:11-6 and N.J.A.C. 5:34-6.1(a), the Qualified Purchasing Agent, QPA, approved the aforementione...