Dept/ Agency: Water and Sewer Utilities
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Final Quantities Change Order #1/Amend Resolution #7R12-c (s) adopted on June 11, 2019
Purpose: To execute Contract Close out Change Order #1 Phase- I (B) Sewer Cleaning and Rehabilitation - Contract 13-WS2017
Entity Name: Montana Construction Corporation, Inc.
Entity Address: 80 Contant Avenue, Lodi, New Jersey 07644
Contract Amount: Not to exceed $6,406,231.12
Funding Source: Capital Budget/Department of Water and Sewer Utilities
Contract Period: 848 calendar days to final completion from the date of the issuance of a written Notice to Proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
(X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Resolution 7R12-c(S) adopted on June 11, 2019 authorized a contract in the amount of $6,743,122.00 for a period of (320) calendar days from the date of the issuance of a written Notice to Proceed.
Contract Close out Change Order #1 will reduce the contract amount by $336,890.88 for a new total contract amount not to exceed $6,406,231.12 and increase the contract period by (528) calendar days for a new completion period of (848) calendar days from the date of the issuance of a written Notice to Proceed.
body
WHEREAS, Resolution 7R12-c(S) adopted on June 11, 2019 authorized the award of Contract 13-WS2017 to, Montana Construction Corporation, Inc., 80 Contant Avenue, Lodi, New Jersey 07644, in the amount of $6,743,122.00, in accordance with the Local Public Contracts Law, N.J.S.A. 40A:11-1 et seq.; and
WHEREAS, the Contract 13-WS2017, was completed with a net reduction of Three Hundred Thirty-Six Thousand Eight Hundred Ninety Dollars and Eighty-Eight Cents ($336,890.88) due to final quantity adjustments and an additional (528) calendar da...