Title
Dept/ Agency: Engineering
Action:  ( x  ) Ratifying     (X) Authorizing     ( x  ) Amending
Type of Service:  Change Order 
Purpose: Wilson Avenue Reconstruction Eastern Phase Project
Entity Name:  Underground Utilities Corp 
Entity Address:  711 Commerce Road, Linden, New Jersey 07036 
Contract Amount: $2,747,825.80
Funding Source:               N/A          
Contract Period:  July 22, 2013 through December 1, 2014
Contract Basis: ( X  ) Bid   (   ) State Vendor   (   ) Prof.  Ser.   (   ) EUS   
(   ) Fair & Open   (   ) No Reportable Contributions   (   ) RFP   (   ) RFQ 
(   ) Private Sale   (   ) Grant   (   ) Sub-recipient   (   ) n/a    
Additional Information: 
 Resolution 7R4-a adopted March 20, 2013.
Extends time to complete  Contract No. 08-2010, Wilson Avenue Reconstruction Eastern Phase Project, to December 1, 2014.
body
          WHEREAS, Resolution No. 7R4-A, adopted March 20, 2013, authorized the Director of the Department of Engineering to accept the bid proposal and execute Contract No. 08-2010, Wilson Avenue Reconstruction Eastern Phase Project with Underground Utilities Corp., 711 Commerce Road, Linden, New Jersey 07036, in an amount not to exceed $2,747,825.80; and      
      WHEREAS, a Notice to Proceed was issue on July 22, 2013, which date constituted the commencement of the contract term, which was 365 days hence; and      
      WHEREAS, due to delays due to weather and heavy traffic conditions within the work site, the Department of Engineering wishes to extend the contract term through December 1, 2014, in order to complete all street resurfacing along Wilson Avenue, complete all punch list items and allow the New Jersey Department of Transportation to perform final inspection on the project; and      
      WHEREAS, this Change Order No. 1 will not increase the total contract amount; and      
      WHEREAS, the attached Change Order No. 1 to Contract No. 08-2010, Wilson Avenue Reconstruction Eas...