Dept/ Agency: Engineering
Action: (X) Ratifying (X) Authorizing (X) Amending
Type of Service: Professional Services Contract
Purpose: Central Avenue Bridge over NJ Transit City Subway - Preliminary Design Phase Project- Change Order #1, Contract Amendment for Extension of Time
Entity Name: Michael Baker International, Inc.
Entity Address: One Gateway Center, Suite 2330, Newark, New Jersey 07102
Contract Amount: Not to exceed $1,422,445.34
Funding Source: Federal Highway Administration (FHWA)/New Jersey Department of Transportation (NJDOT)
Contract Period: June 22, 2024 through March 22, 2025
Contract Basis: ( ) Bid ( ) State Vendor (X) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Addition Information:
Resolution 7R3-a adopted on March 15, 2023 awarded a contract in an amount not to exceed $1,422,445.34 for a contract period of (365) days from the effective date of the written Notice to Proceed or June 22, 2023 through June 22, 2024.
Contract #2022-12PS, for the Central Avenue Bridge over NJ Transit City Subway, Local Preliminary Design Project requires additional time to complete the preliminary design phase.
This Amending Resolution will extend the term of the contract by nine (9) additional months, from June 22, 2024 through March 22, 2025, at no additional cost to the City of Newark.
body
WHEREAS, Resolution No. 7R3-a, adopted March 15, 2023, authorized the Acting Director of the Department of Engineering to accept the proposal dated June 9, 2022 submitted by Michael Baker International Inc., One Gateway Center, Suite 2330, Newark, New Jersey 07102, and execute Contract No. 2022-12PS, for the Central Avenue Bridge Over NJ Transit City Subway, Local Preliminary Design Project, in the amount not to exceed $1,422,445.34; and
WHEREAS, the original contract term was 3...