File #: 08-145    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 9/9/2008 In control: Engineering
On agenda: 9/17/2008 Final action: 9/17/2008
Title: Dept/ Agency: Department of Engineering AUTHORIZING / AMENDING Type of Service: Change Order #1 to Contract #04-2007 Broad Street Streetscape - Phase II Purpose: Amending 7Rx 080107 to Increase Quantities of Materials Entity Name: Berto Construction, Inc. Address: 625 Leesville Avenue, Rahway, NJ 07065 Original Contract Amount: $3,394,057.43 New Increase Amount: $477,724.90 Total Contract Amount: $3,871,782.33 Contract Period: Contract Period Extended to End October 31, 2008 Contract Basis: Bid 1 Bid Received Additional Comments: N/A Invitation: Acting Engineering Director, September 16, 2008

Title

Dept/ Agency:  Department of Engineering

AUTHORIZING / AMENDING 

Type of Service:  Change Order #1 to Contract #04-2007

Broad Street Streetscape - Phase II

Purpose:  Amending 7Rx 080107 to Increase Quantities of Materials

Entity Name:  Berto Construction, Inc.

Address:  625 Leesville Avenue, Rahway, NJ  07065

Original Contract Amount:  $3,394,057.43

New Increase Amount: $477,724.90

Total Contract Amount:  $3,871,782.33

Contract Period: Contract Period Extended to End October 31, 2008

Contract Basis: Bid    

1 Bid Received

Additional Comments:  N/A

Invitation: Acting Engineering Director, September 16, 2008