File #: 12-1180    Version: 1 Name: Contract 03-WS2012 (Re-bid) Sidewalk Restoration Award
Type: Resolution Status: Filed
File created: 5/15/2012 In control: Water Sewer Utility
On agenda: 7/3/2012 Final action: 7/3/2012
Title: Dept/ Agency: Water & Sewer Utilities Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Bid Contract Purpose: Concrete Sidewalk Restoration over Water/Sewer Utility Excavations Entity Name: Nagi Construction Co., Inc. Entity Address: 51 Great Hills Road, Millburn, New Jersey 07041 Contract Amount: $192,000.00 Funding Source: City of Newark Budget/Water & Sewer Utilities Partial Cert. provided for $100,000.00/Remainder $92,000.00 to be appropriated in the 2012 and 2013 Municipal Budget Contract Period: 365 days from notice to proceed Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Bids Received: 2
Title
Dept/ Agency: Water & Sewer Utilities
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Bid Contract
Purpose: Concrete Sidewalk Restoration over Water/Sewer Utility Excavations
Entity Name: Nagi Construction Co., Inc.
Entity Address: 51 Great Hills Road, Millburn, New Jersey 07041
Contract Amount: $192,000.00
Funding Source: City of Newark Budget/Water & Sewer Utilities Partial Cert. provided for $100,000.00/Remainder $92,000.00 to be appropriated in the 2012 and 2013 Municipal Budget
Contract Period: 365 days from notice to proceed
Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Bids Received: 2
body

WHEREAS, the City of Newark advertised Contract 03-WS2012 Concrete Sidewalk Restoration over Water/Sewer Utility Excavations on March 21, 2012 and the contract included the replacement of approximately 14,000 square feet of concrete sidewalk construction, and on April 11, 2012, two (2) bids were received for the said project in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq., and both bids were rejected due to having material defects that cannot be cured; and

WHEREAS, on April 24, 2012 the City of Newark re-advertised Contract 03-WS2012 (Re-bid) Concrete Sidewalk Restoration over Water/Sewer Utility Excavations, and on May 4, 2012 received two (2) bids for the said project in accordance with the Local Public Contracts Law N.J.S.A. 40A:11-1 et seq.; and

WHEREAS, Nagi Construction Co., Inc., 51 Great Hills Road, Millburn, New Jersey 07041 submitted the lowest responsive and responsible bid according to the specifications and in the amount of $192,000.00; and

WHEREAS, the City of Newark wishes to accept the lowest responsible bid submitted by Nagi Construction Co., Inc., on May 4...