File #: 12-1350    Version: Name: Broad Street Streetscape – Phase 3A Change Order
Type: Resolution Status: Filed
File created: 6/12/2012 In control: Engineering
On agenda: 10/3/2012 Final action: 12/5/2012
Title: Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Change Order/Amend Resolution 2010 Purpose: Broad Street Streetscape - Phase 3A - 2009 Transportation -Enhancement increase funds in the amount of $495,873.86 and extend the term of the contract Entity Name: Berto Construction, Inc. Entity Address: 625 Leesville Avenue, Rahway, New Jersey 07065 Contract Amount: $2,335,455.99 Funding Source: Capital Contract Period: extending term of the contract to October 1, 2012 Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Amending Resolution #7R4-A, adopted September 15, 2010 Deferred 7R4-a 100312 Deferred 7R4-a 101712 Invitation: Engineering Director and Berto’s Administration, November 7, 2012 Def...
Title
Dept/ Agency: Engineering
Action: ( ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Change Order/Amend Resolution 2010
Purpose: Broad Street Streetscape - Phase 3A - 2009 Transportation -Enhancement increase funds in the amount of $495,873.86 and extend the term of the contract
Entity Name: Berto Construction, Inc.
Entity Address: 625 Leesville Avenue, Rahway, New Jersey 07065
Contract Amount: $2,335,455.99
Funding Source: Capital
Contract Period: extending term of the contract to October 1, 2012
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Amending Resolution #7R4-A, adopted September 15, 2010
Deferred 7R4-a 100312
Deferred 7R4-a 101712
Invitation: Engineering Director and Berto’s Administration, November 7, 2012
Deferred 7R4-a 110812
Invitation: Engineering Director and Berto’s Construction Representative, November 19, 2012
No Action Taken, November 20, 2012
body

WHEREAS, Resolution No. 7R4-A, adopted September 15, 2010, authorized the Director of the Department of Engineering to accept the bid proposal and execute Contract No. 18-2009, Broad Street Streetscape - Phase 3A - 2009 Transportation Enhancement, with Berto Construction Inc., 625 Leesville Avenue, Rahway, New Jersey 07065, for the amount of $1,839,582.13; and

WHEREAS, at the request of the Department of Engineering, both decreases and increases in contract quantities, totaling a 27% increase in the contract amount due to field adjustments, revisions and unforeseen field conditions; and

WHEREAS, the changes were related to electrical and traffic signal modifications at Broad Street and Branford Place, and at Broad Street and Franklin Street. In order to provide safe pedestrian crossings at these intersections, traffic ...