File #: 12-2440    Version: 1 Name: UTCS Change Order #1, Contract No. 16-2010(R)
Type: Resolution Status: Filed
File created: 12/27/2012 In control: Engineering
On agenda: 2/6/2013 Final action: 2/6/2013
Title: Dept/ Agency: Engineering Action: ( x ) Ratifying (X) Authorizing ( ) Amending Type of Service: Change Order No. 1/Extend Contract Term Purpose: Traffic Signal Interconnect Entity Name: Daidone Electric, Inc. Entity Address: 200 Raymond Boulevard, Newark, New Jersey 07105 Contract Amount: $1,615,000.00 Funding Source: NJDOT Contract Period: December 14, 2011 - September 1, 2013 Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Change Order amount $0.00. Contract awarded by resolution #7R4-A, adopted July 7, 2011.
Related files: 14-0222
Title
Dept/ Agency: Engineering
Action: ( x ) Ratifying (X) Authorizing ( ) Amending
Type of Service: Change Order No. 1/Extend Contract Term
Purpose: Traffic Signal Interconnect
Entity Name: Daidone Electric, Inc.
Entity Address: 200 Raymond Boulevard, Newark, New Jersey 07105
Contract Amount: $1,615,000.00
Funding Source: NJDOT
Contract Period: December 14, 2011 - September 1, 2013
Contract Basis: ( ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Change Order amount $0.00. Contract awarded by resolution #7R4-A, adopted July 7, 2011.
body

WHEREAS, Resolution No. 7R4-A, adopted July 7, 2011, authorized the Director of the Department of Engineering to accept the bid proposal and execute Contract No. 16-2010R, Construction of UTCS Extension, Traffic Signal System Centralization, Section 4, with Daidone Electric, Inc., 200 Raymond Boulevard,, Newark, New Jersey 07105,, for the amount of $1,615,000.00; and

WHEREAS, on November 21, 2011, the Director of the Department of Engineering issued a formal Notice to Proceed, with December 14, 2011 as the contract commencement date; and

WHEREAS, the contract work has not yet been completed, necessitating an amendment of the term to include an amended termination date of September 1, 2013; and

WHEREAS, at the request of the Department of Engineering, the contractor has proposed contract deductions (offsets) of original contract quantities and costs, totaling $194,996.69,, certain different signal equipment and other additional work, required by field adjustments and other revisions to the traffic signal network totaling $194,996.69, which on the whole do not substantially change the scope of work; and

WHEREAS, the attached Change Order No. 1 to Contract No. 16-2010R, Construction of UTCS ...

Click here for full text