File #: 13-1011    Version: 1 Name: Bismarck Construction Corporation: Renovation of Chestnut Street Fire House (Second Amendment) (2012-2013)
Type: Resolution Status: Filed
File created: 5/22/2013 In control: Engineering
On agenda: 7/3/2013 Final action: 7/3/2013
Title: Dept/ Agency: Engineering Action: (X ) Ratifying (X) Authorizing (X ) Amending Type of Service: Change Order/Amend Resolution Purpose: Renovation of Chestnut Street Fire House, Engine 27/Ladder 4, located at 87-89 Elm Road, Newark, New Jersey 07105 Entity Name: Bismark Construction Corporation Entity Address: 207-209 Berkeley Avenue, Newark, New Jersey 07107 Contract Amount: $3,188,600.00(with an increase of $227,151.83 for a total amount of $3,415,751.83) Funding Source: City of Newark Budget/Engineering Contract Period: February 1, 2012 through October 31, 2013 Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Amending Contract #21-2010 amount from $3,188,600.00 to $3,415,751.83 (Increased by $227,151.83) Resolution 7R4-C adopted May 18, 2011 (Ori...
Related files: 13-0154
Title
Dept/ Agency: Engineering
Action: (X ) Ratifying (X) Authorizing (X ) Amending
Type of Service: Change Order/Amend Resolution
Purpose: Renovation of Chestnut Street Fire House, Engine 27/Ladder 4, located at 87-89 Elm Road, Newark, New Jersey 07105
Entity Name: Bismark Construction Corporation
Entity Address: 207-209 Berkeley Avenue, Newark, New Jersey 07107
Contract Amount: $3,188,600.00(with an increase of $227,151.83 for a total amount of $3,415,751.83)
Funding Source: City of Newark Budget/Engineering
Contract Period: February 1, 2012 through October 31, 2013
Contract Basis: ( X ) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS
( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ
( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a
Additional Information:
Amending Contract #21-2010 amount from $3,188,600.00 to $3,415,751.83 (Increased by $227,151.83)
Resolution 7R4-C adopted May 18, 2011 (Original contract $3,188,600.00)
Resolution 7R4-A adopted March 6, 2013 (Extension of time for completion of work)
body
WHEREAS, Resolution 7R4-C adopted, May 18, 2011, authorized the Director of the Department of Engineering to execute Contract #21-2010 Renovation of Chestnut Street Fire House, Engine 27/Ladder 4, located at 87-89 Elm Road, Newark, New Jersey 07105, with Bismark Construction Corporation, 207-209 Berkeley Avenue, Newark, New Jersey 07107, in the total bid amount of $3,188,600.00 for the period of February 1, 2012 through January 30, 2013; and
WHEREAS, Resolution 7R4-A adopted, March 6, 2013, authorized the Director of the Department of Engineering to amend Contract #21-2010, Renovation of Chestnut Street Fire House, Engine 27/Ladder 4, located at 87-89 Elm Road, Newark, New Jersey 07105, to extend the time period to complete all work through July 27, 2013; and

WHEREAS, due to unforeseen circumstances discovered after the contract was aw...